[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901546":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},901546,583,1,"单选题","（2020年真题）借助机、电、液一体化工作原理,使提升能力可按实际需要进行任意组合配置,解决了常规起重机不能解决的大型构件整体提升技术难题。该吊装方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","缆索系统提升",false,{"key":16,"text":17,"correct":18},"B","液压提升",true,{"key":20,"text":21,"correct":14},"C","汽车起重机提升",{"key":23,"text":24,"correct":14},"D","桥式起重机提升","P102 液压提升。目前多采用“钢绞线悬挂承重、液压提升千斤顶集群、计算机控制同步”方法整体提升（滑移）大型设备与构件。集群液压千斤顶整体提升（滑移〉大型设备与构件技术借助机、电、液一体化工作原理，使提升能力可按实际需要进行任意组合配置，解决了在常规状态下，采用桅杆起重机、移动式起重机所不能解决的大型构件整体提升技术难题，已广泛应用于市政工程建筑工程的相关领域以及设备安装领域。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]