[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901544":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},901544,583,1,"单选题","（2017年考题）某台起重机吊装一设备，已知吊装重物的重量为Q（包括索、吊具的重量）。吊装计算载荷应为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Q",false,{"key":16,"text":17,"correct":18},"B","1.1Q",true,{"key":20,"text":21,"correct":14},"C","1.2Q",{"key":23,"text":24,"correct":14},"D","1.1×1.2Q","在起重工程中，多台起重机联合起吊设备，其中一台起重机承担的计算栽荷，需计入栽荷运动和载荷不均衡的影响，计算荷栽的一般公式为：Q1=K1·K2·Q。一般取动载荷系数K1为1.1，不均衡载荷系数K2为1.1～1.2。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]