[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901434":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},901434,583,1,"单选题","接地极制作安装符合要求的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","常用的为钢管接地极和角钢接地极",true,{"key":16,"text":17,"correct":18},"B","接地极长为5m",false,{"key":20,"text":21,"correct":18},"C","接地极只能垂直敷设",{"key":23,"text":24,"correct":18},"D","接地极的间距不宜小2.5m","教材p367。接地极制作安装。常用的为钢管接地极和角钢接地极。（1）接地极垂直敷设。一般接地极长为2.5m，垂直接地极的间距不宜小于其长度的2 倍，通常为5m。（2）接地极水平敷设。在土壤条件极差的山石地区采用接地极水平敷设。接地装置全部采用镀锌扁钢，所有焊接点处均刷沥青。接地电阻应小于4Ω，超过时，应补增接地装置的长度。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]