[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901278":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},901278,583,1,"单选题","火炬及排气筒塔架制作工艺内容中不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","钢材检查",false,{"key":16,"text":17,"correct":14},"B","焊缝检查",{"key":19,"text":20,"correct":21},"C","整体力学性能试验",true,{"key":23,"text":24,"correct":14},"D","刷油防腐","2020版教材P344 塔架的施工内容，塔架制作属于金属结构工程范围，主要包括钢材检查、焊接、焊缝检查、组对、刷油防腐等内容。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]