[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},901275,583,1,"单选题","球罐安装完后，要进行相应的检验，以保证球罐的质量，正确的质检次序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","焊缝检查→水压试验→气密性实验",true,{"key":16,"text":17,"correct":18},"B","焊缝检查→气密性实验→水压试验",false,{"key":20,"text":21,"correct":18},"C","焊缝检查→气密性实验→气压试验",{"key":23,"text":24,"correct":18},"D","焊缝检查→水压试验→气压试验","2020版教材P338 静置设备与工艺金属结构制作和安装，球罐安装完成后，首先进行焊缝外观检查和内在质量检查，然后进行水压试验，是为了检查球罐的强度、考核球罐组装焊接质量，以保证球罐能够承受设计压力不漏。球罐经过水压试验合格后要再进行一次磁粉探伤或渗透探伤，排除表面裂纹及其他缺陷后，再进行气密性试验。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]