[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901268":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},901268,583,1,"单选题","火炬及排气筒安装中，施工工序的一般要求是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先塔架分片组对焊接，再筒体成型、组对焊接",true,{"key":16,"text":17,"correct":18},"B","先火炬头的安装，再平台梯子制作安装",false,{"key":20,"text":21,"correct":18},"C","先平台梯子制作安装，再塔架筒体拼装",{"key":23,"text":24,"correct":18},"D","先筒体成型、组对焊接，再塔架分片组对焊接","2020版教材P344 本题考查的是静置设备与工艺金属结构制作、安装。火炬及排气筒均包含有塔架、筒体、平台梯子三部分，另外在火炬顶部还要装有火炬头。火炬及排气筒的组装包括制作与组对焊接。一般施工工序为：塔架分片组对焊接；筒体滚圆成型、组对焊接，塔架筒体分段拼装、焊接，火炬及排气筒整体组装、焊接，平台梯子制作安装，火炬头的安装。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]