[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901234":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},901234,583,1,"单选题","夹套管安装就位后，应进行内、外管的吹扫工作。内管一般采用的吹扫介质为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","氮气",false,{"key":16,"text":17,"correct":14},"B","无油压缩空气",{"key":19,"text":20,"correct":14},"C","干燥压缩空气",{"key":22,"text":23,"correct":24},"D","干燥无油压缩空气",true,"2020版教材P301 本题的考点是夹套管安装要求。 夹套管安装构成系统后，应进行内、外管的吹扫工作，凡不能参与吹扫的管道、设备、阀门、仪表等，应拆除或用盲板隔离。内管应用干燥无油压缩空气进行系统吹扫，气体流速不小于20m／s，在管子出口处放置白布进行检查，以无铁锈、脏物为合格。热水夹套系统的吹扫要求同内管。而蒸汽夹套系统用低压蒸汽吹扫，吹扫顺序为先主管、后支管，最后进入夹套管的环隙。操作时需充分暖管，缓慢开启控制阀门升温，恒温60min后连续吹扫10～20min，重复3～4次。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]