[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},901169,583,1,"单选题","生活给水系统在交付使用之前必须进行冲洗和消毒，以下做法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","试压合格后，利用系统内存水进行冲洗，再进行消毒",false,{"key":16,"text":17,"correct":18},"B","冲洗顺序是先室外、后室内；先地下、后地上",true,{"key":20,"text":21,"correct":14},"C","冲洗前可不拆除节流阀、报警阀、孔板和喷嘴",{"key":23,"text":24,"correct":14},"D","消毒用水应在管道中停留12h","2020版教材P224 管道防护及水压试验，“管道冲洗、消毒。生活给水系统管道试压合格后，应将管道系统内存水放空。各配水点与配水件连接后，在交付使用之前必须进行冲洗和消毒。冲洗方法应根据对管道的使用要求、管道内表面污染程度确定。冲洗顺序应先室外，后室内；先地下，后地上。室内部分的冲洗应按配水干管、配水管、配水支管的顺序进行。”",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]