[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},900976,583,1,"单选题","在安装专业措施项目清单中，不在吊装加固项目工作内容及包含范围内的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","行车梁加固",false,{"key":16,"text":17,"correct":14},"B","桥式起重机加固及负荷试验",{"key":19,"text":20,"correct":21},"C","吊装设备吊耳的制作、加固及安装",true,{"key":23,"text":24,"correct":14},"D","整体吊装临时加固件、加固设施拆除、清理","2020版教材P119 措施项目清单的内容吊装加固，吊装加固：行车梁加固；桥式起重机加固及负荷试验；整体吊装临时加固件，加固设施拆除、清理。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]