[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900973":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},900973,583,1,"单选题","按《建设工程工程量清单计价规范》GB50500-2013的规定，当拟建工程有重量大于40t的设备安装时，其专业工程措施项目清单可列项（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","金属抱杆安装拆除、移位",true,{"key":16,"text":17,"correct":18},"B","组装平台",false,{"key":20,"text":21,"correct":18},"C","现场施工图栏",{"key":23,"text":24,"correct":18},"D","二次搬运","2020版教材P122 施工方案、施工方法及计量，当拟建工程有大于40t的设备安装时，措施项目清单可列项“金属抱杆安装拆除、移位”。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]