[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900972":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},900972,583,1,"单选题","当拟建工程中有三类容器制作安装，有超过10MPa的高压管道敷设，措施项目可列项为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","隧道内施工通风、供水、供气、供电、照明及通风",false,{"key":16,"text":17,"correct":14},"B","管道安装充气保护",{"key":19,"text":20,"correct":14},"C","设备、管道施工安全防冻防雨",{"key":22,"text":23,"correct":24},"D","工程系统检测、检验",true,"2020版教材P121 施工方案、施工方法及计量，当拟建工程中有三类容器制作、安装，有超过lOMPa的高压管道敷设时，措施项目清单可列项“工程系统检测、检验”。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]