[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900963":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},900963,583,1,"单选题","依据《通用安装工程工程量计算规范》GB50856-2013的规定，项目编码设置中的第四级编码的数字位数及表示含义为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2位数，表示各分部工程顺序码",false,{"key":16,"text":17,"correct":14},"B","2位数，表示各分项工程顺序码",{"key":19,"text":20,"correct":14},"C","3位数，表示各分部工程顺序码",{"key":22,"text":23,"correct":24},"D","3位数，表示各分项工程顺序码",true,"2020版教材P111 第四级编码表示，第四级编码表示各分部工程的各分项工程，即表示清单项目。采用三位数字（即第七、八、九位数字）表示。如030101001为“台式及仪表机床”，030803001为“高压碳钢管”分项工程。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]