[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},900943,583,1,"单选题","在清单计价项目中，投标人投标报价的共同基础是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工料单价",false,{"key":16,"text":17,"correct":18},"B","工程量清单标明的工程量",true,{"key":20,"text":21,"correct":14},"C","综合单价",{"key":23,"text":24,"correct":14},"D","按拟采用施工方案计算的工程量","2020版教材P114 本题考查的是安装工程计量规定。工程量清单标明的工程量是投标人投标报价的共同基础，投标人工程量必须与招标人提供的工程量一致。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]