[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},900938,583,1,"单选题","对于管道吹扫与清洗，说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管道在压力试验前进行吹扫与清洗",false,{"key":16,"text":17,"correct":14},"B","DN\u003C600mm 的气体管道宜采用水冲洗",{"key":19,"text":20,"correct":14},"C","管道应连同系统内的仪表、阀门进行吹扫",{"key":22,"text":23,"correct":24},"D","吹扫与清洗的顺序应按主管、支管、疏排管依次进行",true,"教材p103。管道系统安装后，在压力试验合格后，应进行吹扫与清洗。一般应符合下列规定：（1）DN≥600mm 的液体或气体管道，宜采用人工清理。（2）DN\u003C600mm 的液体管道，宜采用水冲洗。（3）DN\u003C600mm 的气体管道，宜采用压缩空气吹扫。（4）蒸汽管道应采用蒸汽吹扫，非热力管道不得采用蒸汽吹扫。（7）管道吹洗前的保护措施。应将系统内的仪表、孔板、节流阀、调节阀、电磁阀、阀、止回阀等管道组件暂时拆除，以模拟件或临时短管替代，待管道吹洗合格后再重新复位。对以焊接形式连接的上述阀门、仪表等部件，应采取流经旁路或卸掉阀头及阀座加保护套等保护措施后再进行吹扫与清洗。（8）吹扫与清洗的顺序应按主管、支管、疏排管依次进行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]