[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},900869,583,1,"单选题","某一回转运动的反应釜，工艺要求在负压下工作，釜内壁需采用金属铅防腐蚀，覆盖铅的方法应为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","螺栓固定法",false,{"key":16,"text":17,"correct":14},"B","压板条固定法",{"key":19,"text":20,"correct":14},"C","搪钉固定法",{"key":22,"text":23,"correct":24},"D","搪铅法",true,"2020版教材P91 衬铅:将铅板用搪钉、螺栓或压板固定在设备或被衬工件表面上，再用铅焊条将铅板之间的缝隙焊接起来，形成一层将设备与介质隔离开的铅防腐层，称为衬铅。分别称为搪钉固定法、螺栓固定法和压板条固定法。搪铅:采用氢氧焰将铅条熔融后贴覆在被衬的工件或设备表面上形成具有一定厚度密实的铅层。衬铅的施工方法比搪铅简单，生产周期短，相对成本也低，适用于立面、静荷载和正压下工作;搪铅与设备器壁之间结合均匀且牢固，没有间隙，传热性好，适用于负压、回转运动和震动下工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]