[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},900610,583,1,"单选题","按《通用安装工程计量规范》GB50856-2013 的规定，不属于安全文明施工及其他措施项目的为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建筑工地起重机械的检验检测",false,{"key":16,"text":17,"correct":14},"B","二次搬运",{"key":19,"text":20,"correct":21},"C","平台铺设、拆除",true,{"key":23,"text":24,"correct":14},"D","已完工程及设备保护","平台铺设、拆除，属于安装专业工程措施项目，其他三项属于安全文明施工及其他措施项目。建筑工地起重机械的检验检测，属于安全施工范畴。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]