[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900604":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},900604,583,1,"单选题","根据《通用安装工程计量规范》GB50856-2013 有关项目编码规定，第三级编码表示（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","各专业工程顺序码",false,{"key":16,"text":17,"correct":18},"B","各分部工程顺序码",true,{"key":20,"text":21,"correct":14},"C","各分项工程顺序码",{"key":23,"text":24,"correct":14},"D","清单项目名称顺序码","第三级编码表示各专业工程下的各分部工程。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]