[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},900578,583,1,"单选题","自行式起重机的选用时，根据被吊装设备或构件的就位位置、现场具体情况等确定起重机的站车位置，站车位置一旦确定，则（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可由特性曲线确定起重机的臂长",false,{"key":16,"text":17,"correct":18},"B","可确定起重机的工作幅度",true,{"key":20,"text":21,"correct":14},"C","可确定起重机的计算载荷",{"key":23,"text":24,"correct":14},"D","可确定起重机的最大起升高度","自行式起重机的选用：根据被吊装设备或构件的就位位置、现场具体情况等确定起重机的站车位置，站车位置一旦确定，其工作幅度也就确定了。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]