[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900576":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},900576,583,1,"单选题","两台起重机共同抬吊一个重物，已知重物质量为 100t，索吊具质量为 2t，不均衡载荷系数取上限时，其计算荷载应为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","121t",false,{"key":16,"text":17,"correct":14},"B","132 t",{"key":19,"text":20,"correct":14},"C","123.42t",{"key":22,"text":23,"correct":24},"D","67.32t",true,"在多分支共同抬吊一个重物时。由于工作不同步这种现象称为不均衡。在起重工程中，以不均衡载荷系数计入其影响，一般取不均衡载荷系数 K 为 1.1～1.2。本题规定不均衡载荷系数取上限，即 K = 1.2。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]