[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},900573,583,1,"单选题","某工作现场要求起重机吊装能力为3～100 t，臂长40～80m，使用地点固定、使用周期较长且较经济。一般为单机作业，也可双机抬吊，应选用的吊装方法为（---）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","液压提升法",false,{"key":16,"text":17,"correct":14},"B","桅杆系统吊装",{"key":19,"text":20,"correct":21},"C","塔式起重机吊装",true,{"key":23,"text":24,"correct":14},"D","桥式起重机吊装","塔式起重机吊装的起重吊装能力为 3～100 t，臂长在 40～80 m，常用在使用地点固定、使用周期较长的场合，较经济。一般为单机作业，也可双机抬吊。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]