[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900453":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},900453,583,1,"单选题","(2017年)蒸汽夹套管系统安装完毕后，应用低压蒸汽吹扫，正确的吹扫顺序应为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主管-支管-夹套管环隙",true,{"key":16,"text":17,"correct":18},"B","支管-主管-夹套管环隙",false,{"key":20,"text":21,"correct":18},"C","主管-夹套管环隙-支管",{"key":23,"text":24,"correct":18},"D","支管-夹套管环隙-主管","蒸汽夹套系统用低压蒸汽吹扫.吹扫顺序为先主管、后支管，最后进入夹套管的环隙。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]