[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},900435,583,1,"单选题","(2018年)某空气净化塔塔内设有开孔率较大的筛板，筛板上放置一定数量的轻质小球，吸收剂自上向下喷淋，加湿小球表面进行吸收。该空气净化塔为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","筛板塔",false,{"key":16,"text":17,"correct":14},"B","喷淋塔",{"key":19,"text":20,"correct":14},"C","填料塔",{"key":22,"text":23,"correct":24},"D","湍流塔",true,"湍流塔。塔内设有开孔率较大的筛板，筛板上放置一定数量的轻质小球，相互碰撞，吸收剂自上向下喷淋，加湿小球表面，进行吸收。由于气、液、固三相接触，小球表面液膜不断更新，增大吸收推动力，提高吸收效率。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]