[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900430":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},900430,583,1,"单选题","(2014年)安装吊顶式新风空调箱，以下选项符合规定的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单独设置机房",false,{"key":16,"text":17,"correct":14},"B","因风机为低噪声风机，可不考虑减振措施",{"key":19,"text":20,"correct":21},"C","机组送风口与送风管连接采用帆布软管",true,{"key":23,"text":24,"correct":14},"D","一般情况下吊装机组风量不超过10000m3\u002Fh","(4）吊顶式新风空调箱安装。 1)在机组风量和重量均不太大，而机组的振动又较小的情况下，吊杆顶部采用膨胀螺栓与楼板连接，吊杆底部采用螺扣加装橡胶减振垫与吊装孔连接的办法。对于大风量吊装式新风机组，重量较大，则应采取一定的保证措施。 2）合理考虑机组振动，采取适当的减振措施。 3）机组的送风口与送风管道连接时应采用帆布软管连接形式。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]