[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900414":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},900414,583,1,"单选题","(2018年)依据《通用安装工程工程量计算规范》（GB50856－2013）给排水、采暖、燃气工程工程量计量规则，以下关于室外管道碰头叙述正确的为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不包括挖工作坑，土方回填",false,{"key":16,"text":17,"correct":14},"B","带介质管道碰头不包括开关闸、临时放水管线铺设",{"key":19,"text":20,"correct":21},"C","适用于新建或扩建工程热源、水源、气源管道与原（旧）有管道碰头",true,{"key":23,"text":24,"correct":14},"D","热源管道碰头供、回水接口分别计算","室外管道碰头：①适用于新建或扩建工程热源、水源、气源管道与原（旧）有管道碰头；②室外管道碰头包括挖工作坑、土方回填或暖气沟局部拆除及修复；③带介质管道碰头包括开关闸、临时放水管线铺设等费用；④热源管道碰头每处包括供、回水两个接口；⑤碰头形式指带介质碰头、不带介质碰头。室外管道碰头工程数量按设计图示以处计算，计量单位为“处”。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]