[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900409":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},900409,583,1,"单选题","(2014年)生活给水系统在交付使用之前必须进行冲洗和消毒，以下做法正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","试压合格后，利用系统内存水进行冲洗，再进行消毒",false,{"key":16,"text":17,"correct":18},"B","冲洗顺序是先室外、后室内；先地下、后地上",true,{"key":20,"text":21,"correct":14},"C","冲洗前可不拆除节流阀、报警阀、孔板和喷嘴",{"key":23,"text":24,"correct":14},"D","消毒用水应在管道中停留12h","4）管道冲洗、消毒。生活给水系统管道试压合格后，应将管道系统内存水放空。（A错误）冲洗顺序应先室外，后室内；先地下，后地上。（B正确）冲洗前，应将不允许冲洗的设备和管道与冲洗系统隔离，应对系统的仪表采取保护措施。节流阀、止回阀阀芯和报警阀等应拆除，已安装的孔板、喷嘴、滤网等装置也应拆下保管好，待冲洗后及时复位。（C错误）饮用水管道在使用前用每升水中含20～ 30mg 游离氯的水灌满管道进行消毒，水在管道中停留24h 以上。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]