[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900392":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},900392,583,1,"单选题","(2017年)依据《通用安装工程工程量计算规范》(GB50856-2013)，静置设备安装工程量计量时，根据项目特征以“座”为计量单位的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","金属油罐中拱顶罐制作安装",false,{"key":16,"text":17,"correct":14},"B","球形罐组对安装",{"key":19,"text":20,"correct":14},"C","热交换器设备安装",{"key":22,"text":23,"correct":24},"D","火炬及排气筒制作安装",true,"(9）火炬及排气筒制作安装（项目编码：030307008）， 应根据项目特征（名称，构造形式，材质， 质量，筒体直径，高度，灌浆配合比）， 以“座” 为计量单位， 按设计图示数量计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]