[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900324":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},900324,583,1,"单选题","(2018年)锅炉本体及其附属设备安装完毕后，必须进行水压试验。当锅筒工作压力小于0.8MPa 时，试验压力应为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","锅筒工作压力的1.5 倍，但不小于0.2MPa",true,{"key":16,"text":17,"correct":18},"B","锅筒工作压力的1.4 倍，但不小于0.2MPa",false,{"key":20,"text":21,"correct":18},"C","锅筒工作压力的1.2 倍，但不小于0.2MPa",{"key":23,"text":24,"correct":18},"D","锅筒工作压力的1.1 倍，但不小于0.2MPa","锅炉本体水压试验的试验压力见表4.2.5。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]