[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900322":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},900322,583,1,"单选题","(2018年)依据《通用安装工程工程量计算规范》（GB 50856－2013），工业锅炉脱硫设备及辅助设备安装工程量中以“t”为计量单位的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","烟气换热器",false,{"key":16,"text":17,"correct":14},"B","真空皮带脱水机",{"key":19,"text":20,"correct":21},"C","吸收塔",true,{"key":23,"text":24,"correct":14},"D","旋流器","（20）脱硫设备安装。1）石粉仓、吸收塔应根据项目特征（型号；出力t\u002Fh；容积或直径），以“t”为计量单位，按设计图示质量计算。2）脱硫附属机械及辅助设备应根据项目特征（名称；型号；规格），以“套”为计量单位，按设计图示数量计算。注：脱硫附属机械及辅助设备包括：增压风机、烟气换热器、真空皮带脱水机、旋流器和循环浆液泵的安装。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]