[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900266":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},900266,583,1,"单选题","(2012年)在安装工程施工项目管理实施规划中，施工项目实施规划的核心为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工方案",true,{"key":16,"text":17,"correct":18},"B","施工进度计划",false,{"key":20,"text":21,"correct":18},"C","施工质量计划",{"key":23,"text":24,"correct":18},"D","施工现场平面布置","该题主要考察的是：施工方案，施工方案和施工方法是施工项目管理规划的主要内容之一。施工方案内容一般包括施工流向和施工顺序， 施工阶段划分， 施工方法和施工机械选择等内容。还包括招标文件、施工规范与工程验收规范和设计文件对工程所要求的技术措施而采用的一些施工方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]