[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900259":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},900259,583,1,"单选题","(2012年)按《建设工程工程量清单计价规范》(CB50500-2008)的规定，不属于通用措施项目的为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安全文明施工",false,{"key":16,"text":17,"correct":14},"B","大型机械设备进出场及安拆",{"key":19,"text":20,"correct":21},"C","组装平台制作",true,{"key":23,"text":24,"correct":14},"D","已完工程及设备保护","该题主要考察的是：措施项目，通用措施项目一览表中《建设工程工程量清单计价规范》(GB50500-2008)的规定，通用措施项目包括：安全文明施工（含环境保护、文明施工、安全施工、临时设施）、夜间施工、二次搬运、冬雨季施工、大型机械设备进出场及安拆、施工排水、施工降水、地上、地下设施，建筑物的临时保护设施、已完工程及设备保护。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]