[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900249":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},900249,583,1,"单选题","(2018年)某段装有调节阀的热力管道安装及试压合格后，要进行管道清理。下列表述正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","采用水冲洗方式，按先支管、后主管依次进行清理",false,{"key":16,"text":17,"correct":14},"B","采用压缩空气吹扫方式，按先主管、后支管依次进行清理",{"key":19,"text":20,"correct":14},"C","若调节阀为法兰连接，应采用旁通管方式保护后再进行压缩空气吹扫",{"key":22,"text":23,"correct":24},"D","将非焊接的调节阀拆除后用临时短管代替，再采用水冲洗清理，合格后将阀门复位",true,"吹扫与清洗的顺序应按主管、支管、疏排管依次进行；热力管道，属于高温高压管道，不宜采用压缩空气吹扫；管道吹洗前的保护措施。应将系统内的仪表、孔板、节流阀、调节阀、电磁阀、安全阀、止回阀等管道组件暂时拆除，以模拟件或临时短管替代，待管道吹洗合格后再重新复位。对以焊接形式连接的上述阀门、仪表等部件，应采取流经旁路或卸掉阀头及阀座加保护套等保护措施后再进行吹扫与清洗。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]