[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},900229,583,1,"单选题","(2017年)某台起重机吊装一设备，已知吊装重物的重量为Q（包括索、吊具的重量）。吊装计算载荷应为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Q",false,{"key":16,"text":17,"correct":18},"B","1.1Q",true,{"key":20,"text":21,"correct":14},"C","1.2Q",{"key":23,"text":24,"correct":14},"D","1.1×1.2Q","3）吊装计算载荷。吊装计算载荷（简称计算载荷）等于动载系数乘以吊装载荷。起重吊装工程中常以吊装计算载荷作为计算依据。计算载荷的一般公式为：Qj=K1×K2×Q；一般取动载荷系数K1为1.1。本题为单台起重机吊装，而K2为不均衡载荷系，是在多分支（多台起重机、多套滑轮组等）共同抬吊一个重物时才考虑的，故本题不考虑K2。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]