[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},900225,583,1,"单选题","(2014年)在起重工程设计时，计算荷载计入了动荷载和不均衡荷载的影响。当被吊重物质量为100t，吊索具质量为3t，不均衡荷载系数取下限时，其计算荷载为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","113.3",false,{"key":16,"text":17,"correct":18},"B","124.63",true,{"key":20,"text":21,"correct":14},"C","135.96",{"key":23,"text":24,"correct":14},"D","48.32","该题主要考察的是起重工程的设计计算，在起重工程的设计中，为了计入动荷载、不均衡荷载的影响，常以计算荷载作为计算依据。计算荷载的一般公式为：Qj=K??K??Q，式中，K?是动荷载系数，取1.1；K?是不均衡荷栽系数，取1.1～1.2；Q是设备及吊索具重量。起重机计算荷载=1.1×1.1×(100+3)=124.63(t)。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]