[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-582-44":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":171},{"id":5,"name":6,"category":7,"favorite":8},582,"建设工程计价","建筑工程",0,44,50,2160,[13,38,53,68,82,97,112,127,142,156],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},900079,2,"多选题","（2017年考题）发包人对工程质量有异议，竣工结算仍应按会同约定办理的情形有（ ）。",[19,23,26,30,33],{"key":20,"text":21,"correct":22},"A","工程已竣工验收的",true,{"key":24,"text":25,"correct":22},"B","工程已竣工未验收，但实际投入使用的",{"key":27,"text":28,"correct":29},"C","工程已竣工未验收且未实际投入使用的",false,{"key":31,"text":32,"correct":22},"D","工程停建，对无质量争议的部分",{"key":34,"text":35,"correct":29},"E","工程停建，对有质量争议的部分","ABD","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},900080,"（2018年考题）编制建设项目竣工决算必须满足的条件包括（ ）。",[42,44,46,48,50],{"key":20,"text":43,"correct":22},"经批准的初步设计所决定的工程内容已完成",{"key":24,"text":45,"correct":22},"单项工程或建设项目竣工结算已完成",{"key":27,"text":47,"correct":29},"收尾工程竣工结算已完成",{"key":31,"text":49,"correct":22},"预留费用不超过规定比例",{"key":34,"text":51,"correct":22},"涉及工程质量纠纷事项已处理完毕","ABDE",{"id":54,"libraryId":5,"type":15,"typeLabel":16,"stem":55,"options":56,"answer":67,"analysis":37},900081,"（2015年考题）工程造价咨询人在进行工程造价鉴定时，应自行收集而非由委托人提供的鉴定资料有（ ）。",[57,59,61,63,65],{"key":20,"text":58,"correct":22},"适用于鉴定项目的规章、规范性文件和定额",{"key":24,"text":60,"correct":22},"鉴定项目同期同类型工程的技术经济指标",{"key":27,"text":62,"correct":29},"鉴定项目施工过程中的施工组织、质量、工期等工程资料",{"key":31,"text":64,"correct":29},"鉴定项目的施工合同及补充协议",{"key":34,"text":66,"correct":29},"鉴定项目所涉及实物标的的现场勘验资料","AB",{"id":69,"libraryId":5,"type":15,"typeLabel":16,"stem":70,"options":71,"answer":36,"analysis":37},900082,"（2019年考题）根据2017版FIDIC《施工合同条件》关于工程变更的说法，正确的有（ ）。",[72,74,76,78,80],{"key":20,"text":73,"correct":22},"不论何种变更，均须工程师发出变更指令",{"key":24,"text":75,"correct":22},"在明确构成工程变更的情况下，承包商享有工期顺延和调价权利，无需再发出索赔通知",{"key":27,"text":77,"correct":29},"承包商建议的变更是指承包商基于价值工程主动提出建议而形成的变更",{"key":31,"text":79,"correct":22},"对于变更工程:重新确定费率或价格，在没有可供参考依据且缺乏合同约定的条件下，利润率按5%计取",{"key":34,"text":81,"correct":29},"承包商基于价值工程主动提出建议引起的变更批准后，变更永久工程的设计增加的设计费由发包人承担;",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":96,"analysis":37},900083,"（2017年考题）在国际工程承包中，根据FIDIC《施工合同条件》（1999年版），因工程量变更可以调整合同规定费率或价格的条件包括（ ）。",[86,88,90,92,94],{"key":20,"text":87,"correct":22},"实际工程量比工程量表中规定的工程量的变动大于10%",{"key":24,"text":89,"correct":22},"该工程量的变更与相对应费率的乘积超过了中标金额的0.01%",{"key":27,"text":91,"correct":22},"由于工程量的变动直接造成单位工程费用的变动超过1%",{"key":31,"text":93,"correct":29},"原工程量全剖删减，其替代工程的费用对合司总价无影响",{"key":34,"text":95,"correct":29},"该部分工程量是合同中规定的“固定率项目”","ABC",{"id":98,"libraryId":5,"type":15,"typeLabel":16,"stem":99,"options":100,"answer":111,"analysis":37},900084,"（2020年真题）根据现行《标准设计施工总承包招标文件》工程总承包项目合同中的暂列金额可用于支付签订合同时（）。",[101,103,105,107,109],{"key":20,"text":102,"correct":22},"不可预见的变更设计费用",{"key":24,"text":104,"correct":22},"不可预见的变更施工费用",{"key":27,"text":106,"correct":29},"已知必然发生，但暂时无法确定价格的专业工程费用",{"key":31,"text":108,"correct":29},"已知必然发生，但暂时无法确定价格的工程设备购置费用",{"key":34,"text":110,"correct":22},"以计日工方式计价的工程变更费用","ABE",{"id":113,"libraryId":5,"type":15,"typeLabel":16,"stem":114,"options":115,"answer":126,"analysis":37},900085,"（2020年真题）根据现行财务制度和企业会计准则，新增固定资产价值的内容包括（）",[116,118,120,122,124],{"key":20,"text":117,"correct":29},"专有技术",{"key":24,"text":119,"correct":22},"建设单位管理费",{"key":27,"text":121,"correct":22},"土地征用费",{"key":31,"text":123,"correct":29},"银行存款",{"key":34,"text":125,"correct":22},"建筑工程设计费","BCE",{"id":128,"libraryId":5,"type":15,"typeLabel":16,"stem":129,"options":130,"answer":141,"analysis":37},900086,"（2017年考题）根据财政部、国家发改委、住建部的有关文件，竣工结算的组成文件包括（ ）。",[131,133,135,137,139],{"key":20,"text":132,"correct":29},"工程竣工验收报告",{"key":24,"text":134,"correct":22},"工程竣工图",{"key":27,"text":136,"correct":29},"设计概算施工图预算",{"key":31,"text":138,"correct":29},"工程竣工结算",{"key":34,"text":140,"correct":22},"工程竣工造价对比分析","BE",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":155,"analysis":37},900087,"（2015年考题）下列各项中属于竣工财务决算说明书内容的是（ ）。",[146,148,149,151,153],{"key":20,"text":147,"correct":22},"基本建设项目概况",{"key":24,"text":140,"correct":29},{"key":27,"text":150,"correct":22},"基建结余资金等分配情况",{"key":31,"text":152,"correct":22},"基本建设项目管理及决算中存在的问题、建议",{"key":34,"text":154,"correct":22},"决算与概算的差异和原因分析","ACDE",{"id":157,"libraryId":5,"type":15,"typeLabel":16,"stem":158,"options":159,"answer":170,"analysis":37},900088,"（2016年考题）关于新增固定资产价值的确定，下列说法中正确的有（ ）。",[160,162,164,166,168],{"key":20,"text":161,"correct":29},"以单位工程为对象计算",{"key":24,"text":163,"correct":22},"以验收合格、正式移交生产或使用为前提",{"key":27,"text":165,"correct":29},"分期分批交付生产的工程，按最后一批交付时间统一计算",{"key":31,"text":167,"correct":22},"包括达到固定资产标准不需要安装的设备和工器具的价值",{"key":34,"text":169,"correct":22},"是建设项目竣工投产后所增加的固定资产价值","BDE",[172,176,179,182,185,188],{"id":173,"name":174,"category":7,"favorite":175},1,"领导干部任职前廉政法规知识测试题",92,{"id":177,"name":178,"category":7,"favorite":173},595,"建筑结构与设备",{"id":180,"name":181,"category":7,"favorite":173},715,"招标采购专业知识与法律法规",{"id":183,"name":184,"category":7,"favorite":173},848,"市政方向-通用基础",{"id":186,"name":187,"category":7,"favorite":8},534,"BIM工程师",{"id":189,"name":187,"category":7,"favorite":8},535]