[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-582-43":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":741},{"id":5,"name":6,"category":7,"favorite":8},582,"建设工程计价","建筑工程",0,43,50,2160,[13,38,53,68,83,96,110,125,140,154,169,183,197,211,226,241,256,271,285,300,314,329,343,357,371,386,401,415,429,443,457,471,486,500,515,529,543,558,572,586,600,614,628,642,656,671,685,699,713,727],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},900029,2,"多选题","（2017年考题）在技术改造项目中，可采用生产能力平衡法来确定合理生产规模。下列属于生产能力平衡法的是（ ）。",[19,23,26,30,33],{"key":20,"text":21,"correct":22},"A","盈亏平衡产量分析法",false,{"key":24,"text":25,"correct":22},"B","平均成本法",{"key":27,"text":28,"correct":29},"C","最小公倍数法",true,{"key":31,"text":32,"correct":29},"D","最大工序生产能力法",{"key":34,"text":35,"correct":22},"E","设备系数法","CD","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},900030,"（2016年考题）关于投资决策阶段流动资金的估算，下列说法中正确的有（ ）。",[42,44,46,48,50],{"key":20,"text":43,"correct":29},"流动资金周转额的大小与生产规模及周转速度直接相关",{"key":24,"text":45,"correct":29},"分项详细估算时，需要计算各类流动资产和流动负债的年周转次数",{"key":27,"text":47,"correct":22},"当年发生的流动资金借款应按半年计息",{"key":31,"text":49,"correct":22},"流动资金借款利息应计入建设期贷款利息",{"key":34,"text":51,"correct":22},"不同生产负荷下的流动资金按100%生产负荷下的流动资金乘以生产负荷百分比计算","AB",{"id":54,"libraryId":5,"type":15,"typeLabel":16,"stem":55,"options":56,"answer":67,"analysis":37},900031,"（2018年考题）关于建筑设计对工业项目造价的影响，下列说法正确的有（ ）。",[57,59,61,63,65],{"key":20,"text":58,"correct":22},"建筑周长系数越高，单位面积造价越低",{"key":24,"text":60,"correct":29},"单跨厂房柱间距不变，跨度越大，单位面积造价越低",{"key":27,"text":62,"correct":22},"多跨厂房跨度不变，中跨数目越多，单位面积造价越高",{"key":31,"text":64,"correct":29},"超高层建筑采用框架结构和剪力墙结构比较经济",{"key":34,"text":66,"correct":22},"大中型工业厂房一般选用砌体结构来降低工程造价","BD",{"id":69,"libraryId":5,"type":15,"typeLabel":16,"stem":70,"options":71,"answer":82,"analysis":37},900032,"（2019年考题）以下属于流动资产的是（ ）。",[72,74,76,78,80],{"key":20,"text":73,"correct":29},"存货",{"key":24,"text":75,"correct":29},"库存现金",{"key":27,"text":77,"correct":29},"应收账款",{"key":31,"text":79,"correct":22},"应付账款",{"key":34,"text":81,"correct":29},"预付账款","ABCE",{"id":84,"libraryId":5,"type":15,"typeLabel":16,"stem":85,"options":86,"answer":95,"analysis":37},900033,"（2015年考题）建设规模是影响工程造价的主要因素之一，项目决策阶段合理确定建设规模的主要方法有（ ）。",[87,88,89,91,93],{"key":20,"text":21,"correct":29},{"key":24,"text":25,"correct":29},{"key":27,"text":90,"correct":29},"生产能力平衡法",{"key":31,"text":92,"correct":22},"单位生产能力估算法",{"key":34,"text":94,"correct":22},"回归分析法","ABC",{"id":97,"libraryId":5,"type":15,"typeLabel":16,"stem":98,"options":99,"answer":82,"analysis":37},900034,"（2018年考题）下列估算方法中，不适用于可行性研究阶段投资估算的有（ ）。",[100,102,104,106,108],{"key":20,"text":101,"correct":29},"生产能力指数",{"key":24,"text":103,"correct":29},"比例估算法",{"key":27,"text":105,"correct":29},"系数估算法",{"key":31,"text":107,"correct":22},"指标估算法",{"key":34,"text":109,"correct":29},"混合法",{"id":111,"libraryId":5,"type":15,"typeLabel":16,"stem":112,"options":113,"answer":124,"analysis":37},900035,"（2017年考题）总平面设计中，影响工程造价的主要因素包括（ ）。",[114,116,118,120,122],{"key":20,"text":115,"correct":29},"现场条件",{"key":24,"text":117,"correct":29},"占地面积",{"key":27,"text":119,"correct":22},"工艺设计",{"key":31,"text":121,"correct":29},"功能分区",{"key":34,"text":123,"correct":22},"柱网布置","ABD",{"id":126,"libraryId":5,"type":15,"typeLabel":16,"stem":127,"options":128,"answer":139,"analysis":37},900036,"（2020年真题）在满足建筑物使用要求的前提下，关于设计阶段影响工程造价的因素，下列说法正确的有（）",[129,131,133,135,137],{"key":20,"text":130,"correct":22},"流通空间越大，工业建筑物越经济",{"key":24,"text":132,"correct":29},"建筑层高越高，工程造价越高",{"key":27,"text":134,"correct":29},"对于单跨厂房，当柱间距不变时，跨度越大单位面积造价越低",{"key":31,"text":136,"correct":29},"对于多跨厂房，当跨度不变时，中跨数目越多单位面积造价越低",{"key":34,"text":138,"correct":22},"住宅层数越多，单位面积造价越低","BCD",{"id":141,"libraryId":5,"type":15,"typeLabel":16,"stem":142,"options":143,"answer":95,"analysis":37},900037,"（2015年考题）直接套用概算指标编制单位建筑工程设计概算时，拟建工程应符合的条件包括（ ）。",[144,146,148,150,152],{"key":20,"text":145,"correct":29},"建设地点与概算指标中的工程建设地点相同",{"key":24,"text":147,"correct":29},"工程特征与概算指标中的工程特征基本相同",{"key":27,"text":149,"correct":29},"建筑面积与概算指标中的工程建筑面积相差不大",{"key":31,"text":151,"correct":22},"建造时间与概算指标中工程建造时间相近",{"key":34,"text":153,"correct":22},"物价水平与概算指标中工程的物价水平基本相同",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":168,"analysis":37},900038,"（2018年考题）在编制单位建筑工程施工图预算时，一般应计入综合取定的措施项目费的有（ ）。",[158,160,162,164,166],{"key":20,"text":159,"correct":22},"施工降水费用",{"key":24,"text":161,"correct":29},"冬雨季施工增加费",{"key":27,"text":163,"correct":29},"夜间施工增加费",{"key":31,"text":165,"correct":22},"模板费用",{"key":34,"text":167,"correct":22},"脚手架费用","BC",{"id":170,"libraryId":5,"type":15,"typeLabel":16,"stem":171,"options":172,"answer":52,"analysis":37},900039,"（2015年考题）关于施工图预算对投资方的作用，下列说法中正确的有（ ）。",[173,175,177,179,181],{"key":20,"text":174,"correct":29},"是控制施工图设计不突破设计概算的重要措施",{"key":24,"text":176,"correct":29},"是控制造价及资金合理使用的依据",{"key":27,"text":178,"correct":22},"是投标报价的基础",{"key":31,"text":180,"correct":22},"是与施工预算进行“两算”对比的依据",{"key":34,"text":182,"correct":22},"是调配施工力量、组织材料供应的依据",{"id":184,"libraryId":5,"type":15,"typeLabel":16,"stem":185,"options":186,"answer":36,"analysis":37},900040,"（2016年考题）施工图预算对投资方、施工企业都具有十分重要的作用。下列选项中仅属于对施工企业作用的有（ ）。",[187,189,191,193,195],{"key":20,"text":188,"correct":22},"确定合同价款的依据",{"key":24,"text":190,"correct":22},"控制资金合理使用的依据",{"key":27,"text":192,"correct":29},"控制工程施工成本的依据",{"key":31,"text":194,"correct":29},"调配施工力量的依据",{"key":34,"text":196,"correct":22},"办理工程结算的依据",{"id":198,"libraryId":5,"type":15,"typeLabel":16,"stem":199,"options":200,"answer":168,"analysis":37},900041,"（2017年考题）采用全费用综合单价法编制施工图预算，下列说法中正确的有（ ）。",[201,203,205,207,209],{"key":20,"text":202,"correct":22},"计算直接费后编制工料分析表",{"key":24,"text":204,"correct":29},"全费用综合单价中应包括规费和税金",{"key":27,"text":206,"correct":29},"综合计取的措施项目费以分部分项工程费和可计量的措施项目费之和为基数计算",{"key":31,"text":208,"correct":22},"编制综合单价分析表时，工料机消耗量与单价均应来自预算定额",{"key":34,"text":210,"correct":22},"分部分项工程量与措施项目费之和即为建筑安装工程施工图预算费用",{"id":212,"libraryId":5,"type":15,"typeLabel":16,"stem":213,"options":214,"answer":225,"analysis":37},900042,"（2020年真题）关于施工图预算的编制，下列说法正确的有（）",[215,217,219,221,223],{"key":20,"text":216,"correct":29},"施工图总预算应控制在已批准的设计总概算范围内",{"key":24,"text":218,"correct":22},"施工图预算采用的价格水平应与设计概算编制时期的保持一致",{"key":27,"text":220,"correct":22},"只有一个单项工程的建设项目应采用三级预算编制形式",{"key":31,"text":222,"correct":29},"单项工程综合预算由组成该单项工程的各个单位工程预算汇总而成",{"key":34,"text":224,"correct":29},"施工图预算编制时已发生的工程建设其他费按合理发生金额列计","ADE",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":240,"analysis":37},900043,"（2020年真题）下列费用中，属于招标工程量清单中其他项目清单编制内容的是（）",[230,232,234,236,238],{"key":20,"text":231,"correct":29},"暂列金额",{"key":24,"text":233,"correct":29},"暂估价",{"key":27,"text":235,"correct":29},"计日工",{"key":31,"text":237,"correct":29},"总承包服务费",{"key":34,"text":239,"correct":22},"措施费","ABCD",{"id":242,"libraryId":5,"type":15,"typeLabel":16,"stem":243,"options":244,"answer":255,"analysis":37},900044,"（2017年考题）根据《建设工程工程量清单计价规范》（GB50500-2013），关于分部分项工程项目清单的编制，下列说法中正确的有（ ）。",[245,247,249,251,253],{"key":20,"text":246,"correct":22},"项目编码应按照计算规范附录给定的编码",{"key":24,"text":248,"correct":22},"项目名称应按照计算规范附录给定的名称",{"key":27,"text":250,"correct":29},"项目特征描述应满足确定综合单价的需要",{"key":31,"text":252,"correct":22},"补充项目应有两个或两个以上的计量单位",{"key":34,"text":254,"correct":29},"工程量计算应按一定顺序依次进行","CE",{"id":257,"libraryId":5,"type":15,"typeLabel":16,"stem":258,"options":259,"answer":270,"analysis":37},900045,"（2015年考题）关于招标工程量清单的编制，下列说法正确的是（ ）。",[260,262,264,266,268],{"key":20,"text":261,"correct":29},"若采用标准图集能够全部满足项目特征描述的要求，项目特征描述可直接采用“详见xx图”的方式",{"key":24,"text":263,"correct":29},"措施项目清单的编制需考虑工程本身、水文、气象、环境、安全等多种因素",{"key":27,"text":265,"correct":22},"以“项”为计量单位的专业工程暂估价一般应包括管理费、规费、利润、税金等",{"key":31,"text":267,"correct":29},"工程量清单总说明应对工程概况、工程招标及分包范围、工程质量要求等进行描述",{"key":34,"text":269,"correct":29},"工程量清单编制依据包括设计文件、招标文件、施工现场情况、常规施工方案等","ABDE",{"id":272,"libraryId":5,"type":15,"typeLabel":16,"stem":273,"options":274,"answer":124,"analysis":37},900046,"（2015年考题）根据《建设工程工程量清单计价规范》（GB50500-2013），招标控制价中综合单价中应考虑的风险因素包括（ ）。",[275,277,279,281,283],{"key":20,"text":276,"correct":29},"项目管理的复杂性",{"key":24,"text":278,"correct":29},"项目的技术难度",{"key":27,"text":280,"correct":22},"人工单价的市场变化",{"key":31,"text":282,"correct":29},"材料价格的市场风险",{"key":34,"text":284,"correct":22},"税金、规费的政策变化",{"id":286,"libraryId":5,"type":15,"typeLabel":16,"stem":287,"options":288,"answer":299,"analysis":37},900047,"（2018年考题）关于工程施工项目最高投标限价编制的注意事项，下列说法正确的有（ ）。",[289,291,293,295,297],{"key":20,"text":290,"correct":29},"未采用工程造价管理机关发布的工程造价信息时，应予以说明",{"key":24,"text":292,"correct":22},"施工机械设备的选型应本着经济实用、平均有效的原则确定",{"key":27,"text":294,"correct":22},"暂估价中的材料单价应通过市场调查确定",{"key":31,"text":296,"correct":29},"不可竞争措施项目费应按国家有关规定计算",{"key":34,"text":298,"correct":22},"竞争性措施项目费应依据经专家论证确认的施工组织设计或施工方案确定","AD",{"id":301,"libraryId":5,"type":15,"typeLabel":16,"stem":302,"options":303,"answer":95,"analysis":37},900048,"（2016年考题）关于招标分部分项工程量清单的项目特征描述，应遵循的编制原则有（ ）。",[304,306,308,310,312],{"key":20,"text":305,"correct":29},"按专业工程量计算规范附录的规定，结合拟建工程实际描述",{"key":24,"text":307,"correct":29},"其他独有特征，由清单编制人视项目具体情况确定",{"key":27,"text":309,"correct":29},"要满足确定综合单价的需要",{"key":31,"text":311,"correct":22},"应详细描述分部分项工程的施工工艺和方法",{"key":34,"text":313,"correct":22},"对于采用标准图集的项目，可直接描述为“详见##图集”",{"id":315,"libraryId":5,"type":15,"typeLabel":16,"stem":316,"options":317,"answer":328,"analysis":37},900049,"（2017年考题）关于施工投标报价中下列说法中正确的有（ ）。",[318,320,322,324,326],{"key":20,"text":319,"correct":22},"投标人应逐项计算工程量，复核工程量清单",{"key":24,"text":321,"correct":22},"投标人应修改错误的工程量，并通知招标人",{"key":27,"text":323,"correct":29},"投标人可以不向招标人提出复核工程量中发现的遗漏",{"key":31,"text":325,"correct":29},"投标人可以通过复核防止由于订货超量带来的浪费",{"key":34,"text":327,"correct":29},"投标人应根据复核工程量的结果选择适用的施工设备","CDE",{"id":330,"libraryId":5,"type":15,"typeLabel":16,"stem":331,"options":332,"answer":139,"analysis":37},900050,"（2017年考题）根据我国现行施工招标投标管理规定，投标有效期的确定一般应考虑的因素有（ ）。",[333,335,337,339,341],{"key":20,"text":334,"correct":22},"投标报价需要的时间",{"key":24,"text":336,"correct":29},"组织评标需要的时间",{"key":27,"text":338,"correct":29},"确定中标人需要的时间",{"key":31,"text":340,"correct":29},"签订合同需要的时间",{"key":34,"text":342,"correct":22},"提交履约保证金需要的时间",{"id":344,"libraryId":5,"type":15,"typeLabel":16,"stem":345,"options":346,"answer":225,"analysis":37},900051,"（2018年考题）投标人在递交投标交件后,其投标保证金按规定不予退还的情形有（ ）。",[347,349,351,353,355],{"key":20,"text":348,"correct":29},"投标人在投标有效期内撤销投标文件的",{"key":24,"text":350,"correct":22},"投标人拒绝延长投标有效期的",{"key":27,"text":352,"correct":22},"投标人在投标截止日前修改投标文件的",{"key":31,"text":354,"correct":29},"中标后无故拒签合同协议书的",{"key":34,"text":356,"correct":29},"中标后未按招标文件规定提交履约担保的",{"id":358,"libraryId":5,"type":15,"typeLabel":16,"stem":359,"options":360,"answer":240,"analysis":37},900052,"（2015年考题）复核工程量是投标人编制投标报价前的一项重要工作。通过复核工程量，便于投标人（ ）。",[361,363,365,367,369],{"key":20,"text":362,"correct":29},"决定报价尺度",{"key":24,"text":364,"correct":29},"采取合适的施工方法",{"key":27,"text":366,"correct":29},"选用合适的施工机具",{"key":31,"text":368,"correct":29},"决定投入劳动力数量",{"key":34,"text":370,"correct":22},"选用合适的承包方式",{"id":372,"libraryId":5,"type":15,"typeLabel":16,"stem":373,"options":374,"answer":385,"analysis":37},900053,"（2016年考题）投标文件应当对招标文件作出实质性响应的内容有（ ）。",[375,377,379,381,383],{"key":20,"text":376,"correct":22},"报价",{"key":24,"text":378,"correct":29},"工期",{"key":27,"text":380,"correct":29},"投标有效期",{"key":31,"text":382,"correct":29},"质量要求",{"key":34,"text":384,"correct":29},"招标范围","BCDE",{"id":387,"libraryId":5,"type":15,"typeLabel":16,"stem":388,"options":389,"answer":400,"analysis":37},900054,"（2020年真题）投标人在确定综合单价时需要注意的事项有（）。",[390,392,394,396,398],{"key":20,"text":391,"correct":29},"清单项目特征描述",{"key":24,"text":393,"correct":22},"清单项目的编码顺序",{"key":27,"text":395,"correct":29},"材料暂估价的处理",{"key":31,"text":397,"correct":29},"材料、设备市场价格的变化风险",{"key":34,"text":399,"correct":22},"税金、规费的变化风险","ACD",{"id":402,"libraryId":5,"type":15,"typeLabel":16,"stem":403,"options":404,"answer":139,"analysis":37},900055,"（2015年考题）在评标过程中，评标委员会可以要求投标人对投标文件有关文件作出必要澄清、说明和补充的情形包括（ ）。",[405,407,409,411,413],{"key":20,"text":406,"correct":22},"投标文件未经单位负责人签字",{"key":24,"text":408,"correct":29},"对同类问题表述不一致",{"key":27,"text":410,"correct":29},"投标文件中有含义不明确的内容",{"key":31,"text":412,"correct":29},"有明显的计算错误",{"key":34,"text":414,"correct":22},"投标人主动提出的澄清说明",{"id":416,"libraryId":5,"type":15,"typeLabel":16,"stem":417,"options":418,"answer":82,"analysis":37},900056,"（2016年考题）根据《招投标法实施条例》，关于依法必须招标项目中标候选人的公示，下列说法中正确的有（ ）。",[419,421,423,425,427],{"key":20,"text":420,"correct":29},"应公示中标候选人",{"key":24,"text":422,"correct":29},"公示对象是全部中标候选人",{"key":27,"text":424,"correct":29},"公示期不得少于3日",{"key":31,"text":426,"correct":22},"公示在开标后的第二天发布",{"key":34,"text":428,"correct":29},"对有业绩信誉条件的项目，其业绩信誉情况应一并进行公示",{"id":430,"libraryId":5,"type":15,"typeLabel":16,"stem":431,"options":432,"answer":299,"analysis":37},900057,"（2017年考题）依法必须招标的工程，对投标保证金的退还，下列处置方式正确的有（ ）。",[433,435,437,439,441],{"key":20,"text":434,"correct":29},"中标人无正当理由拒签合同的，投标保证金不予退还",{"key":24,"text":436,"correct":22},"投标人无正当理由拒签合同的，应向中标人退还投标保证金",{"key":27,"text":438,"correct":22},"招标人与中标人签订合同的，应在合同签订后向中标人退还投标保证金",{"key":31,"text":440,"correct":29},"招标人与中标人签订合同的，应向未中标人退还投标保证金及利息",{"key":34,"text":442,"correct":22},"未中标人的投标保证金，应在中标通知书发书同时退还",{"id":444,"libraryId":5,"type":15,"typeLabel":16,"stem":445,"options":446,"answer":124,"analysis":37},900058,"（2020年真题）关于招标人与中标人合同的签订，下列说法正确的有（）。",[447,449,451,453,455],{"key":20,"text":448,"correct":29},"双方按照招标文件和投标文件订立书面合同",{"key":24,"text":450,"correct":29},"双方在投标有效期内并在自中标通知书发出之日起30日内签订施工合同",{"key":27,"text":452,"correct":22},"招标人要求中标人按中标下浮3%后签订施工合同",{"key":31,"text":454,"correct":29},"中标人无正当理由拒绝签订合同的，招标人可不退还其投标保证金",{"key":34,"text":456,"correct":22},"招标人在与中标人签订合同后5日内，向所有投标人退还投标保证金",{"id":458,"libraryId":5,"type":15,"typeLabel":16,"stem":459,"options":460,"answer":225,"analysis":37},900059,"（2020年真题）根据《建设工程施工合同（示范文本）》（GF-2017-0201），下列变化应纳入工程变更范围的有（）",[461,463,465,467,469],{"key":20,"text":462,"correct":29},"改变墙体厚度",{"key":24,"text":464,"correct":22},"工程设备价格上涨",{"key":27,"text":466,"correct":22},"转由他人实施土石方工程",{"key":31,"text":468,"correct":29},"提高地基沉降控制标准",{"key":34,"text":470,"correct":29},"增加排水沟长度",{"id":472,"libraryId":5,"type":15,"typeLabel":16,"stem":473,"options":474,"answer":485,"analysis":37},900060,"（2020年真题）关于承包人原因导致的工期延误期间合同价款的调整，下列说法正确的有（）。",[475,477,479,481,483],{"key":20,"text":476,"correct":22},"国家政策变化引起工程造价增加的应调增合同价款",{"key":24,"text":478,"correct":29},"国家政策变化引起工程造价降低的应调减合同价款",{"key":27,"text":480,"correct":22},"使用价格调整公式调价时，以计划进度日期指数为现行价格指数",{"key":31,"text":482,"correct":22},"使用价格调整公式调价时，以实际进度日期指数为现行价格指数",{"key":34,"text":484,"correct":29},"使用价格调整公式调价时，以计划进度日期与实际进度日期两个指数中较低者作为调价指数","BE",{"id":487,"libraryId":5,"type":15,"typeLabel":16,"stem":488,"options":489,"answer":225,"analysis":37},900061,"（2019年考题）下列费用中，承包人可以索赔的有（ ）。",[490,492,494,496,498],{"key":20,"text":491,"correct":29},"法定增长的人工费",{"key":24,"text":493,"correct":22},"承包人原因导致工效降低增加的机械使用费",{"key":27,"text":495,"correct":22},"承包人垫资施工的垫资利息",{"key":31,"text":497,"correct":29},"发包人拖延支付工程款的利息",{"key":34,"text":499,"correct":29},"发包人错误扣款的利息",{"id":501,"libraryId":5,"type":15,"typeLabel":16,"stem":502,"options":503,"answer":514,"analysis":37},900062,"（2015年考题）根据《标准施工招标文件》（2007）版，承包人有可能同时获得工期和费用补偿的事件有（ ）。",[504,506,508,510,512],{"key":20,"text":505,"correct":29},"发包方延期提供施工图纸",{"key":24,"text":507,"correct":22},"因不可抗力造成的工期延误",{"key":27,"text":509,"correct":29},"甲供设备未按时进场导致停工",{"key":31,"text":511,"correct":29},"监理对覆盖的隐藏工程重新检查且结果合格",{"key":34,"text":513,"correct":29},"施工中发现文物古迹","ACDE",{"id":516,"libraryId":5,"type":15,"typeLabel":16,"stem":517,"options":518,"answer":400,"analysis":37},900063,"（2015年考题）根据《建设工程工程量清单计价规范》（GB50500-2013），关于工程变更价款的调整方法，下列说法中正确的有（ ）。",[519,521,523,525,527],{"key":20,"text":520,"correct":29},"工程变更导致已标价工程量清单项目的工程量变化小于15%，仍采用原价格",{"key":24,"text":522,"correct":22},"已标价的工程量清单中没有相同或类似的工程变更项目，由发包人提出变更工程项目的总价和单价",{"key":27,"text":524,"correct":29},"安全文明施工费按照实际发生变化的措施项目并依据国家或省级、行业建设主管部门的规定进行调整",{"key":31,"text":526,"correct":29},"采用单价方式计算的措施费，按照分部分项工程费的调整方法确定变更单价",{"key":34,"text":528,"correct":22},"按系数计算的措施项目费均应按照实际发生变化的措施项目调整，系数不得浮动",{"id":530,"libraryId":5,"type":15,"typeLabel":16,"stem":531,"options":532,"answer":124,"analysis":37},900064,"（2016年考题）根据《建设工程工程量清单计价规范》（GB50500--2013），关于单价合同措施项目费的调整，下列说法中正确的有（ ）。",[533,535,537,539,541],{"key":20,"text":534,"correct":29},"设计变更引起措施项目发生变化的，可以调整措施项目费",{"key":24,"text":536,"correct":29},"招标工程量清单分部分项工程漏项引起措施项目发生变化的，可以调整措施项目费",{"key":27,"text":538,"correct":22},"招标工程量清单措施项目缺项的，不应调整措施项目费",{"key":31,"text":540,"correct":29},"承包人提出调整措施项目费的，应事先将实施方案报发包人批准",{"key":34,"text":542,"correct":22},"措施项目费的调整方法与分部分项工程费的调整方法相同",{"id":544,"libraryId":5,"type":15,"typeLabel":16,"stem":545,"options":546,"answer":557,"analysis":37},900065,"（2017年考题）根据《建设工程工程量清单计价规范》（GB-50500-2013），关于计日工费的确认和支付，下列说法中正确的有（ ）。",[547,549,551,553,555],{"key":20,"text":548,"correct":22},"承包人应按照确认的计日工现场签证报告核实该关项目的工程数量和单价",{"key":24,"text":550,"correct":29},"己标价工程量清单中有该类计日工单价的。按该单价计算",{"key":27,"text":552,"correct":22},"已标价工程量清单中没有该类计日工单价的，按承包人报价计算",{"key":31,"text":554,"correct":29},"计日工价款应列入同期进度款支付",{"key":34,"text":556,"correct":29},"发包人通知承包人以计日工方式实施的零星工作，承包人应予执行","BDE",{"id":559,"libraryId":5,"type":15,"typeLabel":16,"stem":560,"options":561,"answer":485,"analysis":37},900066,"（2016年考题）根据《标准施工招标文件》（2007年版）通用合同条款，承包人可能同时获得工期和费用补偿、但不能获得利润补偿的索赔事件有（ ）。",[562,564,566,568,570],{"key":20,"text":563,"correct":22},"延迟提供施工场地",{"key":24,"text":565,"correct":29},"发包人更换其提供的不合格设备",{"key":27,"text":567,"correct":22},"发包人负责的材料延迟提供",{"key":31,"text":569,"correct":22},"监理人指令错误",{"key":34,"text":571,"correct":29},"施工中发现文物",{"id":573,"libraryId":5,"type":15,"typeLabel":16,"stem":574,"options":575,"answer":168,"analysis":37},900067,"（2017年考题）下列资料中，可以作为施工发承包双方提出和处理索赔直接依据的有（ ）。",[576,578,580,582,584],{"key":20,"text":577,"correct":22},"未在合同中约定的工程量所在地地方性法规",{"key":24,"text":579,"correct":29},"工程施工合同文件",{"key":27,"text":581,"correct":29},"合同中约定的非强制性标准",{"key":31,"text":583,"correct":22},"现场签证",{"key":34,"text":585,"correct":22},"合同中未明确规定的地方定额",{"id":587,"libraryId":5,"type":15,"typeLabel":16,"stem":588,"options":589,"answer":95,"analysis":37},900068,"（2018年考题）.根据《建设工程施工合同（示范文本）》（GF-2013-0201）,下列事项应纳入工程变更范国的有（ ）。",[590,592,594,596,598],{"key":20,"text":591,"correct":29},"改变工程的标高",{"key":24,"text":593,"correct":29},"改变工程的实施顺序",{"key":27,"text":595,"correct":29},"提高合同中的工作质量标准",{"key":31,"text":597,"correct":22},"将合同中的某项工作转由他人实施",{"key":34,"text":599,"correct":22},"工程设备价格的变化",{"id":601,"libraryId":5,"type":15,"typeLabel":16,"stem":602,"options":603,"answer":139,"analysis":37},900069,"（2016年考题）支持承包人工程索赔成立的基本条件有（ ）。",[604,606,608,610,612],{"key":20,"text":605,"correct":22},"合同履行过程中承包人没有违约行为",{"key":24,"text":607,"correct":29},"索赔事件已造成承包人直接经济损失或工期延误",{"key":27,"text":609,"correct":29},"索赔事件是因非承包人的原因引起的",{"key":31,"text":611,"correct":29},"承包人已按合同规定提交了索赔意向通知、索赔报告及相关证明材料",{"key":34,"text":613,"correct":22},"发包人已按合同规定给予了承包人答复",{"id":615,"libraryId":5,"type":15,"typeLabel":16,"stem":616,"options":617,"answer":514,"analysis":37},900070,"（2018年考题）因发包人原因导致工程延期时，下列索赔事件能够成立的有（ ）",[618,620,622,624,626],{"key":20,"text":619,"correct":29},"材料超期储存费用索赔",{"key":24,"text":621,"correct":22},"材料保管不善造成的损坏费用索赔",{"key":27,"text":623,"correct":29},"现场管理费索赔",{"key":31,"text":625,"correct":29},"保险费索赔",{"key":34,"text":627,"correct":29},"保函手续费索赔",{"id":629,"libraryId":5,"type":15,"typeLabel":16,"stem":630,"options":631,"answer":270,"analysis":37},900071,"（2018年考题）承包人提交的已完工程进度款支付申请中，应计入本周期完成合同价款中的有（ ）",[632,634,636,638,640],{"key":20,"text":633,"correct":29},"本周期已完成单价项目的金额",{"key":24,"text":635,"correct":29},"本周期应支付的总价项目的金额",{"key":27,"text":637,"correct":22},"本周期应扣回的预付款",{"key":31,"text":639,"correct":29},"本周期应支付的安全文明施工费",{"key":34,"text":641,"correct":29},"本周期完成的计日工价款",{"id":643,"libraryId":5,"type":15,"typeLabel":16,"stem":644,"options":645,"answer":328,"analysis":37},900072,"（2018年考题）下列情形中,当事人提出解除合司，人民法院应予支持的有（ ）。",[646,648,650,652,654],{"key":20,"text":647,"correct":22},"发包人提供的建筑材料不满足承包人要求,承包人请求解除合同",{"key":24,"text":649,"correct":22},"发包人延期28天支付工程款,承包人请求解除合间",{"key":27,"text":651,"correct":29},"承包人以行为表明不履行合同主要义务,发包人请求解除合同。",{"key":31,"text":653,"correct":29},"承包人拒绝修复已完不合格工程,发包人请求解除合同",{"key":34,"text":655,"correct":29},"承包人将工程违法分包,发包人请求解除合同",{"id":657,"libraryId":5,"type":15,"typeLabel":16,"stem":658,"options":659,"answer":670,"analysis":37},900073,"（2020年真题）发包人未按规定程序支付竣工结算款项的，承包人可以（）。",[660,662,664,666,668],{"key":20,"text":661,"correct":29},"催发包人支付",{"key":24,"text":663,"correct":29},"获得延迟支付利息的权利",{"key":27,"text":665,"correct":22},"直接将工程折价",{"key":31,"text":667,"correct":22},"直接将工程拍卖",{"key":34,"text":669,"correct":29},"就工程拍卖价获得优先受偿权","ABE",{"id":672,"libraryId":5,"type":15,"typeLabel":16,"stem":673,"options":674,"answer":124,"analysis":37},900074,"（2020年真题）为保证建设工程仲裁协议有效，合同双方签订的仲裁协议中必须包括的内容有（）。",[675,677,679,681,683],{"key":20,"text":676,"correct":29},"请求仲裁的意思表达",{"key":24,"text":678,"correct":29},"仲裁事项",{"key":27,"text":680,"correct":22},"选定的仲裁员",{"key":31,"text":682,"correct":29},"选定的仲裁委员会",{"key":34,"text":684,"correct":22},"仲裁结果的执行方式",{"id":686,"libraryId":5,"type":15,"typeLabel":16,"stem":687,"options":688,"answer":82,"analysis":37},900075,"（2016年考题）工程造价咨询人开展工程造价司法鉴定工作时，正确的做法有（ ）。",[689,691,693,695,697],{"key":20,"text":690,"correct":29},"应按仲裁、诉讼程序和要求进行鉴定",{"key":24,"text":692,"correct":29},"应依法出庭接受鉴定项目方当事人对鉴定意向书的质询",{"key":27,"text":694,"correct":29},"应自行收集适用于鉴定项目的工程造价信息",{"key":31,"text":696,"correct":22},"应自行对现场进行勘验",{"key":34,"text":698,"correct":29},"是鉴定项目一方当事人、代理人的，应自行回避",{"id":700,"libraryId":5,"type":15,"typeLabel":16,"stem":701,"options":702,"answer":225,"analysis":37},900076,"（2015年考题）采用工程量清单计价的工程，在办理建设工程结算时，工程量计算的原则和方法有（ ）。",[703,705,707,709,711],{"key":20,"text":704,"correct":29},"不符合质量要求的工程不予计量",{"key":24,"text":706,"correct":22},"应按工程量清单计量规范的要求进行计量",{"key":27,"text":708,"correct":22},"无论何种原因，超出合同工程范围的工程均不予计量",{"key":31,"text":710,"correct":29},"因承包人原因造成的返工工程不予计量",{"key":34,"text":712,"correct":29},"应按合同的约定对承包人完成合同工程的数量进行计算和确认",{"id":714,"libraryId":5,"type":15,"typeLabel":16,"stem":715,"options":716,"answer":95,"analysis":37},900077,"（2016年考题）承包人应在每个计量周期到期后，向发包人提交已完工程进度款支付申请，支付申请包括的内容有（ ）。",[717,719,721,723,725],{"key":20,"text":718,"correct":29},"累计已完成的合同价款",{"key":24,"text":720,"correct":29},"本期合计完成的合同价款",{"key":27,"text":722,"correct":29},"本期合计应扣减的金额",{"key":31,"text":724,"correct":22},"累计已调整的合同金额",{"key":34,"text":726,"correct":22},"预计下期将完成的合同价款",{"id":728,"libraryId":5,"type":15,"typeLabel":16,"stem":729,"options":730,"answer":400,"analysis":37},900078,"（2017年考题）根据建设工程工程量清单计价规范GB-50500-2013），关于工程竣工结算的计价原则，下列说法正确的是（ ）。",[731,733,735,737,739],{"key":20,"text":732,"correct":29},"计日工按发包人实际签证确认的事项计算",{"key":24,"text":734,"correct":22},"总承包服务依据合同约定金额计算，不得调整",{"key":27,"text":736,"correct":29},"暂列金额应减去工程价款调整金额计算，余额归发包人",{"key":31,"text":738,"correct":29},"规费和税金应按国家或省级、行业建设主管部门的规定计算",{"key":34,"text":740,"correct":22},"总价措施项目应依据合同约定的项目和金额计算，不得调整",[742,746,749,752,755,758],{"id":743,"name":744,"category":7,"favorite":745},1,"领导干部任职前廉政法规知识测试题",92,{"id":747,"name":748,"category":7,"favorite":743},595,"建筑结构与设备",{"id":750,"name":751,"category":7,"favorite":743},715,"招标采购专业知识与法律法规",{"id":753,"name":754,"category":7,"favorite":743},848,"市政方向-通用基础",{"id":756,"name":757,"category":7,"favorite":8},534,"BIM工程师",{"id":759,"name":757,"category":7,"favorite":8},535]