[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-582-32":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":684},{"id":5,"name":6,"category":7,"favorite":8},582,"建设工程计价","建筑工程",0,32,50,2160,[13,34,42,50,62,74,86,98,110,122,134,146,158,170,182,194,206,218,230,242,254,266,278,290,308,323,338,353,368,382,396,411,426,441,456,470,484,499,513,528,543,557,572,586,601,615,627,641,655,669],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":27,"analysis":33},899421,1,"单选题","（2019年考题）根据《建设工程质量保证全管理办法》（建质[2017138号），质量保证金总预留比例不得高于工程价款结算总额的（ ）。",[19,23,26,30],{"key":20,"text":21,"correct":22},"A","19%",false,{"key":24,"text":25,"correct":22},"B","2%",{"key":27,"text":28,"correct":29},"C","3%",true,{"key":31,"text":32,"correct":22},"D","5%","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":31,"analysis":33},899422,"（2019年考题）关于合同价款的期中支付，下列说法正确的是（ ）。 A.进度款支付周期应与发包人实际的工程计量周期一致 B.已标价工程量清单中单价项目结算价款应按承包人确认的工程量计算C承包人现场签证金额不应列入期中支付进度款，在竣工结算时一并处理 D.进度款的支付按期中结算价款总额和约定比例计算，一般不低于60%，不高于90%",[38,39,40,41],{"key":20,"text":20,"correct":22},{"key":24,"text":24,"correct":22},{"key":27,"text":27,"correct":22},{"key":31,"text":31,"correct":29},{"id":43,"libraryId":5,"type":15,"typeLabel":16,"stem":44,"options":45,"answer":31,"analysis":33},899423,"（2019年考题）关于预付款担保的说法，正确的是（ ）。 A.预付款担保的形式必须为银行保函B预付款担保的担保金额必须高于预付款 C.在预付款的扣回过程中担保金额保持不变D预付款保函在预付款扣回之前必须保持有效",[46,47,48,49],{"key":20,"text":20,"correct":22},{"key":24,"text":24,"correct":22},{"key":27,"text":27,"correct":22},{"key":31,"text":31,"correct":29},{"id":51,"libraryId":5,"type":15,"typeLabel":16,"stem":52,"options":53,"answer":24,"analysis":33},899424,"（2016年考题）根据《建设项目工程总承包合同示范文本》（GF-2011-0216），下列关于变更程序的说法中正确的是（ ）。",[54,56,58,60],{"key":20,"text":55,"correct":22},"发包人要求的变更，应事先以书面或口头形式通知承包人",{"key":24,"text":57,"correct":29},"承包人接到发包人变更通知后，有义务在规定时间内向发包人提交书面建议报告",{"key":27,"text":59,"correct":22},"承包人有义务接受发包人要求的变更，无须通过建议报告表达不支持的观点",{"key":31,"text":61,"correct":22},"承包人提交变更建议报告后，在等待发包人回复的时间内，可停止相关工作",{"id":63,"libraryId":5,"type":15,"typeLabel":16,"stem":64,"options":65,"answer":24,"analysis":33},899425,"（2015年考题）根据FIDIC《施工合同条件》（1999版），关于合同价款调整的规定，下列说法中正确的是（ ）。",[66,68,70,72],{"key":20,"text":67,"correct":22},"工程量的变更与对应费率的乘积超过了中标总金额的1%时才予调整",{"key":24,"text":69,"correct":29},"实际测量工程量比工程量表中工程量变动大于10%时，可调整相应单价",{"key":27,"text":71,"correct":22},"工程师要求改变施工顺序的，不应调整合同价款",{"key":31,"text":73,"correct":22},"承包人配合工程检验所发生的剥露和覆盖，不应调整合同价款",{"id":75,"libraryId":5,"type":15,"typeLabel":16,"stem":76,"options":77,"answer":31,"analysis":33},899426,"（2016年考题）FIDIC施工合同条件规定，如果承包商不能按时收到业主的付款，承包商有权就未付款额收取延误支付期间的融资费。融资费计息方式是（ ）。",[78,80,82,84],{"key":20,"text":79,"correct":22},"按星期计算单利",{"key":24,"text":81,"correct":22},"按星期计算复利",{"key":27,"text":83,"correct":22},"按月计算单利",{"key":31,"text":85,"correct":29},"按月计算复利",{"id":87,"libraryId":5,"type":15,"typeLabel":16,"stem":88,"options":89,"answer":24,"analysis":33},899427,"（2017年考题）根据《建设项目工程总成本合同示范文本（试行）》（GF-2011-0216），下列变更事项，属于采购变更的是（ ）。",[90,92,94,96],{"key":20,"text":91,"correct":22},"对设备规格和数量的调整",{"key":24,"text":93,"correct":29},"改变检查、检验、检测、试验地点",{"key":27,"text":95,"correct":22},"重新进行竣工试验",{"key":31,"text":97,"correct":22},"对配套工程系统的工艺调整",{"id":99,"libraryId":5,"type":15,"typeLabel":16,"stem":100,"options":101,"answer":20,"analysis":33},899428,"（2016年考题）根据《建设项目工程总承包合同示范文本》（GB-2011-0216），下列变更事项中属于设计变更的是（ ）。",[102,104,106,108],{"key":20,"text":103,"correct":29},"基准控制点的调整",{"key":24,"text":105,"correct":22},"备品备件采购数量的调整",{"key":27,"text":107,"correct":22},"新增加的施工障碍处理",{"key":31,"text":109,"correct":22},"增加的附加试验",{"id":111,"libraryId":5,"type":15,"typeLabel":16,"stem":112,"options":113,"answer":27,"analysis":33},899429,"（2017年考题）根据FIDIC《施工合同文件》（1999版）通用合同条件，关于发包人对保留金的保留和返还，下列说法中正确的是（ ）。",[114,116,118,120],{"key":20,"text":115,"correct":22},"每次其中支付时扣留2.5%~5%作为保留金",{"key":24,"text":117,"correct":22},"签发整个工程的接收证书后，返还40%的保留金",{"key":27,"text":119,"correct":29},"工程最后一个缺陷通知期满后，返还剩余的保留金",{"key":31,"text":121,"correct":22},"如承包人有尚未完成的工作，不应返还剩余的保证金",{"id":123,"libraryId":5,"type":15,"typeLabel":16,"stem":124,"options":125,"answer":27,"analysis":33},899430,"（2015年考题）关于建设工程施工合同索赔，下列说法中正确的是（ ）。",[126,128,130,132],{"key":20,"text":127,"correct":22},"发包人可以在索赔事件发生后暂不通知承包人，待工程结算时一并处理",{"key":24,"text":129,"correct":22},"发包人向承包人提出索赔，承包人无权要求发包人补充提供索赔理由和证据",{"key":27,"text":131,"correct":29},"承包人在收到发包人的索赔资料后，未在规定时间内作出答复，视为该索赔事件成立",{"key":31,"text":133,"correct":22},"承包人未在索赔事件发生后的规定时间内发出索赔通知的，应免除发包人的一切责任",{"id":135,"libraryId":5,"type":15,"typeLabel":16,"stem":136,"options":137,"answer":24,"analysis":33},899431,"（2015年考题）关于建设工程总承包合同价款的支付，下列说法正确的是（ ）。",[138,140,142,144],{"key":20,"text":139,"correct":22},"预付款扣完后，由于工程尚未竣工，发包人可以不退还预付款保函",{"key":24,"text":141,"correct":29},"未约定预付款保函的，发包人在合同生效后规定时间内向承包人支付预付款金额",{"key":27,"text":143,"correct":22},"发包人延误付款，应自延误之日起按同期存款利率向承包人支付延期付款利息",{"key":31,"text":145,"correct":22},"发包人延误付款的，承包人有权直接暂停施工",{"id":147,"libraryId":5,"type":15,"typeLabel":16,"stem":148,"options":149,"answer":24,"analysis":33},899432,"（2020年真题）根据2017版FIDIC《施工合同条件》，关于国际工程工程变更与合同价款调整，下列说法正确的是（）。",[150,152,154,156],{"key":20,"text":151,"correct":22},"合同中任何工作的工程量变化均能调整合同价款",{"key":24,"text":153,"correct":29},"不论何种变更,均须由工程师发出变更指令",{"key":27,"text":155,"correct":22},"在明确构成工程变更的情况下，承包商仍须按程序发出索赔通知",{"key":31,"text":157,"correct":22},"承包商提出的对业主有利的工程变更建议书的编制费用，应由业主承担",{"id":159,"libraryId":5,"type":15,"typeLabel":16,"stem":160,"options":161,"answer":27,"analysis":33},899433,"（2020年真题）根据现行《标准设计施工总承包招标文件》，选用暂估价 （A）条款时，若发包人在价格清单中给定暂估价的材料，不属于依法必须招标的，则其价格与暂估价的差额应经确认后计入合同价款，履行该确认职能的应是（）。",[162,164,166,168],{"key":20,"text":163,"correct":22},"发包人",{"key":24,"text":165,"correct":22},"监理人",{"key":27,"text":167,"correct":29},"总承包人",{"key":31,"text":169,"correct":22},"材料供应商",{"id":171,"libraryId":5,"type":15,"typeLabel":16,"stem":172,"options":173,"answer":20,"analysis":33},899434,"（2018年考题）竣工决算文件中，主要反映竣工工程建设成果和经验，全面考核分析工程投资与造价的书面总结文件是（ ）",[174,176,178,180],{"key":20,"text":175,"correct":29},"竣工财务决算说明书",{"key":24,"text":177,"correct":22},"竣工财务决算报表",{"key":27,"text":179,"correct":22},"工程竣工造价对比分析",{"key":31,"text":181,"correct":22},"工程竣工验收报告",{"id":183,"libraryId":5,"type":15,"typeLabel":16,"stem":184,"options":185,"answer":24,"analysis":33},899435,"（2019年考题）在建设项目竣工决算报表中，用于考核和分析投资效果，落实结余资金，并作为报告上级核销基本建设支出依据的是（ ）。",[186,188,190,192],{"key":20,"text":187,"correct":22},"基本建设项目概况表",{"key":24,"text":189,"correct":29},"基本建设项目竣工财务决算表",{"key":27,"text":191,"correct":22},"基本建设项目交付使用资产总表",{"key":31,"text":193,"correct":22},"基本建设项目交付使用资产明细表",{"id":195,"libraryId":5,"type":15,"typeLabel":16,"stem":196,"options":197,"answer":20,"analysis":33},899436,"（2020年真题）某建设项目由 A、B两车间组成，其中A车间的建筑工程费6000万元，安装工程费2000万元，需安装设备费2400万元;B车间建筑工程费2000万元，安装工程费1000万元，需安装设备费用1200万元;该建设项目的土地征用费2000万元，则A车间应分摊的土地征用费是（）万元",[198,200,202,204],{"key":20,"text":199,"correct":29},"1500.00",{"key":24,"text":201,"correct":22},"1454.55",{"key":27,"text":203,"correct":22},"1424.66",{"key":31,"text":205,"correct":22},"1090.91",{"id":207,"libraryId":5,"type":15,"typeLabel":16,"stem":208,"options":209,"answer":24,"analysis":33},899437,"（2017年考题）下列竣工财务决算说明书的内容，一般在项目概况部分予以说明的是（ ）。",[210,212,214,216],{"key":20,"text":211,"correct":22},"项目资金计划及到位情况",{"key":24,"text":213,"correct":29},"项目进度、质量情况",{"key":27,"text":215,"correct":22},"项目建设资金使用与结余情况",{"key":31,"text":217,"correct":22},"主要技术经济指标的分析、计算情况",{"id":219,"libraryId":5,"type":15,"typeLabel":16,"stem":220,"options":221,"answer":31,"analysis":33},899438,"（2016年考题）关于建设工程竣工图的绘制和形成，下列说法中正确的是（ ）。",[222,224,226,228],{"key":20,"text":223,"correct":22},"凡按图竣工没有变动的，由发包人在原施工图上加盖“竣工图”标志",{"key":24,"text":225,"correct":22},"凡在施工过程中发生设计变更的，一律重新绘制竣工图",{"key":27,"text":227,"correct":22},"平面布置发生重大改变的，一律由设计单位负责重新绘制竣工图",{"key":31,"text":229,"correct":29},"重新绘制的新图，应加盖“竣工图”标志",{"id":231,"libraryId":5,"type":15,"typeLabel":16,"stem":232,"options":233,"answer":27,"analysis":33},899439,"（2015年考题）关于建设项目竣工运营后的新增资产，下列说法正确的是（ ）。项目名称建筑工程费（万元）安装工程费（万元）需安装设备费（万元）建设单位管理费（万元）建设项目6000 1000 3000 210K车间2000 500 1500",[234,236,238,240],{"key":20,"text":235,"correct":22},"新增资产按资产性质分为固定资产、流动资产和无形资产三大类",{"key":24,"text":237,"correct":22},"分期分批交付生产或使用的工程，待工程全部交付使用后，一次性计算新增固定资产增值",{"key":27,"text":239,"correct":29},"凡购置的达到固定资产标准不需安装的工器具，应在交付使用后计入新增固定资产",{"key":31,"text":241,"correct":22},"企业库存现金、存货及建设单位管理费中未计入固定资产的各项费用等，应在交付使用后计入新增流动资产价值",{"id":243,"libraryId":5,"type":15,"typeLabel":16,"stem":244,"options":245,"answer":27,"analysis":33},899440,"（2017年考题）某工业建设项目及其中K车间的各项建设费用如下表所示。则K车间应分摊的建设单位管理费为（ ）。",[246,248,250,252],{"key":20,"text":247,"correct":22},"70",{"key":24,"text":249,"correct":22},"75",{"key":27,"text":251,"correct":29},"84",{"key":31,"text":253,"correct":22},"105",{"id":255,"libraryId":5,"type":15,"typeLabel":16,"stem":256,"options":257,"answer":31,"analysis":33},899441,"（2016年考题）竣工财务决算的基本建设项目概况表中，应列入非经营性项目转出投资支出的项目是（ ）。",[258,260,262,264],{"key":20,"text":259,"correct":22},"产权属于本单位的城市绿化",{"key":24,"text":261,"correct":22},"不能形成资产的城市绿化",{"key":27,"text":263,"correct":22},"产权属于本单位的专用道路",{"key":31,"text":265,"correct":29},"产权不属于本单位的专用道路",{"id":267,"libraryId":5,"type":15,"typeLabel":16,"stem":268,"options":269,"answer":24,"analysis":33},899442,"（2016年考题）某建设项目由两个单项工程组成，其竣工结算的有关费用如下表所示。已知该项目建设单位管理费、土地征用费、建筑设计费、工艺设计费分别为100、120、60、40万元。则该单项工程B的新增固定资产价值是（ ）万元。",[270,272,274,276],{"key":20,"text":271,"correct":22},"3132.5",{"key":24,"text":273,"correct":29},"3135",{"key":27,"text":275,"correct":22},"3137.5",{"key":31,"text":277,"correct":22},"3165",{"id":279,"libraryId":5,"type":15,"typeLabel":16,"stem":280,"options":281,"answer":31,"analysis":33},899443,"（2020年真题）根据《基本建设项目建设成本管理规定》，建设项目的建设成本包括（）",[282,284,286,288],{"key":20,"text":283,"correct":22},"为项目配套的专用送变电站投资",{"key":24,"text":285,"correct":22},"非经营性项目转出投资支出",{"key":27,"text":287,"correct":22},"非经营性的农村饮水工程",{"key":31,"text":289,"correct":29},"项目建设管理费",{"id":291,"libraryId":5,"type":292,"typeLabel":293,"stem":294,"options":295,"answer":307,"analysis":33},899444,2,"多选题","(2014年)国产非标准设备按其成本估算其原价时，下列计算式中正确的有（）",[296,298,300,302,304],{"key":20,"text":297,"correct":22},"材料费=材料净重×每吨材料综合价",{"key":24,"text":299,"correct":29},"加工费=设备总重量×设备每单位重量加工费",{"key":27,"text":301,"correct":29},"辅助材料费=设备总重量×辅助材料费指标",{"key":31,"text":303,"correct":22},"增值税=进项税额-当期销项税额",{"key":305,"text":306,"correct":29},"E","当期销项税额=销售额×适用增值税率","BCE",{"id":309,"libraryId":5,"type":292,"typeLabel":293,"stem":310,"options":311,"answer":322,"analysis":33},899445,"(2015年)关于设备购置费的构成和计算，下列说法中正确的有( )。",[312,314,316,318,320],{"key":20,"text":313,"correct":22},"国产标准设备的原价中，一般不包含备件的价格",{"key":24,"text":315,"correct":29},"成本计算估价法常用于非标准设备原价的价格",{"key":27,"text":317,"correct":22},"进口设备原价是指进口设备到岸价",{"key":31,"text":319,"correct":29},"国产非标准设备原价中包含非标准设备设计费",{"key":305,"text":321,"correct":29},"达到固定资产标准的工器具，其购置费用应计入设备购置费中","BDE",{"id":324,"libraryId":5,"type":292,"typeLabel":293,"stem":325,"options":326,"answer":337,"analysis":33},899446,"(2016年)关于生产准备及开办费，下列说法中正确的有()。",[327,329,331,333,335],{"key":20,"text":328,"correct":29},"包括自行组织培训和委托其他单位培训的相关费用",{"key":24,"text":330,"correct":22},"包括正常生产所需的生产办公家具用具的购置费用",{"key":27,"text":332,"correct":22},"包括正常生活所需的生活家具用具的购置费用",{"key":31,"text":334,"correct":22},"包括含备品备件在内的第一套不够固定资产标准的生产工具购置费用",{"key":305,"text":336,"correct":29},"可按设计定员乘以人均生产准备费指标计算","AE",{"id":339,"libraryId":5,"type":292,"typeLabel":293,"stem":340,"options":341,"answer":352,"analysis":33},899447,"(2013年)下列费用项目中，以“到岸价+关税+消费税”为基数，乘以各自给定费（税）率进行计算的有()。",[342,344,346,348,350],{"key":20,"text":343,"correct":22},"外贸手续费",{"key":24,"text":345,"correct":22},"关税",{"key":27,"text":347,"correct":29},"消费税",{"key":31,"text":349,"correct":29},"增值税",{"key":305,"text":351,"correct":29},"车辆购置税","CDE",{"id":354,"libraryId":5,"type":292,"typeLabel":293,"stem":355,"options":356,"answer":367,"analysis":33},899448,"(2016年)下列费用中应计入到设备运杂费的有()。",[357,359,361,363,365],{"key":20,"text":358,"correct":29},"设备保管人员工资",{"key":24,"text":360,"correct":29},"设备采购人员工资",{"key":27,"text":362,"correct":22},"设备自生产厂家运至工地仓库的运费、装卸费",{"key":31,"text":364,"correct":29},"运输中的设备包装支出",{"key":305,"text":366,"correct":29},"设备仓库所占用的固定资产使用费","ABDE",{"id":369,"libraryId":5,"type":292,"typeLabel":293,"stem":370,"options":371,"answer":381,"analysis":33},899449,"(2018年)构成进口设备原价的费用项目中，应以到岸价为计算基数的有（ ）。",[372,374,376,378,379],{"key":20,"text":373,"correct":22},"国际运费",{"key":24,"text":375,"correct":22},"进口环节增值税",{"key":27,"text":377,"correct":22},"银行财务费",{"key":31,"text":343,"correct":29},{"key":305,"text":380,"correct":29},"进口关税","DE",{"id":383,"libraryId":5,"type":292,"typeLabel":293,"stem":384,"options":385,"answer":307,"analysis":33},899450,"(2012年)国际贸易中，CFR交货方式下买方的基本义务有()。",[386,388,390,392,394],{"key":20,"text":387,"correct":22},"负责租船订舱",{"key":24,"text":389,"correct":29},"承担货物在装运港越过船舷以后的一切风险",{"key":27,"text":391,"correct":29},"承担运输途中因遭遇风险引起的额外费用",{"key":31,"text":393,"correct":22},"在合同约定的装运港领受货物",{"key":305,"text":395,"correct":29},"办理进口清关手续",{"id":397,"libraryId":5,"type":292,"typeLabel":293,"stem":398,"options":399,"answer":410,"analysis":33},899451,"（2019年真题）非标准设备原价中，能作为利润取费基数的是（ ）",[400,402,404,406,408],{"key":20,"text":401,"correct":29},"辅助材料费",{"key":24,"text":403,"correct":29},"废品损失费",{"key":27,"text":405,"correct":29},"包装费",{"key":31,"text":407,"correct":22},"外购配套件费",{"key":305,"text":409,"correct":29},"专用工具费","ABCE",{"id":412,"libraryId":5,"type":292,"typeLabel":293,"stem":413,"options":414,"answer":425,"analysis":33},899453,"(2014年)按我国现行建筑安装工程费用项目组成的规定，下列属于企业管理费内容的有（）",[415,417,419,421,423],{"key":20,"text":416,"correct":29},"企业管理人员办公用的文具、纸张等费用",{"key":24,"text":418,"correct":22},"企业施工生成和管理使用的属于固定资产的交通工具的购置、维修费",{"key":27,"text":420,"correct":22},"对建筑以及材料、构件和建筑安装进行特殊签定检查所发生的检验试验费",{"key":31,"text":422,"correct":29},"按全部职工工资总额比例计提的工会经费",{"key":305,"text":424,"correct":29},"为施工生产筹集资金、履约担保所发生的财务费用","ADE",{"id":427,"libraryId":5,"type":292,"typeLabel":293,"stem":428,"options":429,"answer":440,"analysis":33},899454,"(2015年)根据我国现行建筑安装工程费用项目组成的规定，下列费用中属于安全文明施工中临时设施费的有()。",[430,432,434,436,438],{"key":20,"text":431,"correct":29},"现场采用砖砌围挡的安砌费用",{"key":24,"text":433,"correct":22},"现场围挡的墙面美化费用",{"key":27,"text":435,"correct":22},"施工现场的操作场地的硬化费用",{"key":31,"text":437,"correct":29},"施工现场规定范围内临时简易道路的铺设费用",{"key":305,"text":439,"correct":22},"地下室施工时所采用的照明设备的安拆费用","AD",{"id":442,"libraryId":5,"type":292,"typeLabel":293,"stem":443,"options":444,"answer":455,"analysis":33},899455,"(2016年)应予计量的措施项目费包括()。",[445,447,449,451,453],{"key":20,"text":446,"correct":29},"垂直运输费",{"key":24,"text":448,"correct":29},"排水.降水费",{"key":27,"text":450,"correct":22},"冬雨季施工增加费",{"key":31,"text":452,"correct":22},"临时设施费",{"key":305,"text":454,"correct":29},"超高施工增加费","ABE",{"id":457,"libraryId":5,"type":292,"typeLabel":293,"stem":458,"options":459,"answer":307,"analysis":33},899456,"(2013年)关于措施费中超高施工增加费，下列说法正确的有()。",[460,462,464,466,468],{"key":20,"text":461,"correct":22},"单层建筑檐口高度超过30m时计算",{"key":24,"text":463,"correct":29},"多层建筑超过6层时计算",{"key":27,"text":465,"correct":29},"包括建筑超高引起的人工功效降低费",{"key":31,"text":467,"correct":22},"不包括通信联络设备的使用费",{"key":305,"text":469,"correct":29},"按建筑物超高部分建筑面积以“m2”为单位计算",{"id":471,"libraryId":5,"type":292,"typeLabel":293,"stem":472,"options":473,"answer":455,"analysis":33},899457,"(2013年)下列施工企业支出的费用项目中，属于建筑安装工程企业管理费的有()。",[474,476,478,480,482],{"key":20,"text":475,"correct":29},"技术开发费",{"key":24,"text":477,"correct":29},"印花税",{"key":27,"text":479,"correct":22},"已完工程及设备保护费",{"key":31,"text":481,"correct":22},"材料采购及保管费",{"key":305,"text":483,"correct":29},"财产保险费",{"id":485,"libraryId":5,"type":292,"typeLabel":293,"stem":486,"options":487,"answer":498,"analysis":33},899458,"(2014年)下列有关安全文明费的说法中，正确的有（）",[488,490,492,494,496],{"key":20,"text":489,"correct":29},"安全文明施工费包括临时设施费",{"key":24,"text":491,"correct":22},"现场生活用洁净燃料费属于环境保护费",{"key":27,"text":493,"correct":29},"“三宝”、“四口”、“五临边”等防护费用属于安全施工费",{"key":31,"text":495,"correct":22},"消防设施与消防器材的配置费用属于文明施工费",{"key":305,"text":497,"correct":22},"施工现场搭设的临时文化福利用房的费用属于文明施工费","AC",{"id":500,"libraryId":5,"type":292,"typeLabel":293,"stem":501,"options":502,"answer":455,"analysis":33},899459,"(2015年)为了便于措施项目费的确定和调整，通常采用分部分项工程量清单方式编制的措施项目有( )。",[503,505,507,509,511],{"key":20,"text":504,"correct":29},"脚手架工程",{"key":24,"text":506,"correct":29},"垂直运输工程",{"key":27,"text":508,"correct":22},"二次搬运工程",{"key":31,"text":510,"correct":22},"已完工程及设备保护",{"key":305,"text":512,"correct":29},"施工排水降水",{"id":514,"libraryId":5,"type":292,"typeLabel":293,"stem":515,"options":516,"answer":527,"analysis":33},899460,"(2016年)根据我国现行建筑安装工程费用项目组成规定，下列施工企业发生的费用中，应计入企业管理费的是()。",[517,519,521,523,525],{"key":20,"text":518,"correct":29},"建筑材料、构件一般性鉴定检查费",{"key":24,"text":520,"correct":29},"支付给企业离休干部的经费",{"key":27,"text":522,"correct":22},"施工现场工程排污费",{"key":31,"text":524,"correct":29},"履约担保所发生的费用",{"key":305,"text":526,"correct":22},"施工生产用仪器仪表使用费","ABD",{"id":529,"libraryId":5,"type":292,"typeLabel":293,"stem":530,"options":531,"answer":542,"analysis":33},899461,"(2018年)关于国外建筑安装工程费用中的开办费，下列说法正确的有（ ）。",[532,534,536,538,540],{"key":20,"text":533,"correct":29},"开办费项目可以按单项工程分别单独列出",{"key":24,"text":535,"correct":22},"单项工程建筑安装工程量越大，开办费在工程价格中的比例越大",{"key":27,"text":537,"correct":29},"开办费包括的内容因国家和工程的不同而异",{"key":31,"text":539,"correct":29},"开办费项目可以采用分摊进单价的方式报价",{"key":305,"text":541,"correct":22},"第三者责任险投保费一般应作为开办费的构成内容","ACD",{"id":544,"libraryId":5,"type":292,"typeLabel":293,"stem":545,"options":546,"answer":455,"analysis":33},899462,"(2018年)按照费用构成要素划分的建筑安装工程费用项目组成规定，下列费用项目应列入材料费的有()",[547,549,551,553,555],{"key":20,"text":548,"correct":29},"周转材料的摊销、租赁费用",{"key":24,"text":550,"correct":29},"材料运输损耗费用",{"key":27,"text":552,"correct":22},"施工企业对材料进行一般鉴定、检查发生的费用",{"key":31,"text":554,"correct":22},"材料运杂费中的增值税进项税额",{"key":305,"text":556,"correct":29},"材料采购及保管费用",{"id":558,"libraryId":5,"type":292,"typeLabel":293,"stem":559,"options":560,"answer":571,"analysis":33},899463,"（2019年真题）根据我国现行《建安工程造价计价方法》,下列情况可用简易计税方法的是（ ）",[561,563,565,567,569],{"key":20,"text":562,"correct":29},"小规模纳税人发生的应税行为",{"key":24,"text":564,"correct":29},"一般纳税人以清包工方式提供的建筑服务",{"key":27,"text":566,"correct":29},"一般纳税人为甲供工程提供的建筑服务",{"key":31,"text":568,"correct":29},"《施工许可证》注明的开工日期在2016年4月30日前",{"key":305,"text":570,"correct":22},"实际开工日期在2016年4月30日前的建筑工程项目","ABCD",{"id":573,"libraryId":5,"type":292,"typeLabel":293,"stem":574,"options":575,"answer":410,"analysis":33},899466,"(2014年)下列费用中，属于“与项目建设有关的其他建设费用”的有（）",[576,578,580,582,584],{"key":20,"text":577,"correct":29},"建设单位管理费",{"key":24,"text":579,"correct":29},"工程监理费",{"key":27,"text":581,"correct":29},"建设单位临时设施费",{"key":31,"text":583,"correct":22},"施工单位临时设施费",{"key":305,"text":585,"correct":29},"市政公用设施费",{"id":587,"libraryId":5,"type":292,"typeLabel":293,"stem":588,"options":589,"answer":600,"analysis":33},899467,"(2015年)关于建设用地取得及费用，下列说法中正确的有( )。",[590,592,594,596,598],{"key":20,"text":591,"correct":29},"通过出让获得国有土地使用权的方式有招标、拍卖、挂牌和协议",{"key":24,"text":593,"correct":22},"工业、商业、旅游、娱乐用地的土地使用权出让最长年限为40年",{"key":27,"text":595,"correct":29},"以划拨方式取得的土地使用权，因企业改制不再符合划拨用地目录，应实行有偿使用",{"key":31,"text":597,"correct":22},"通过市场机制获得的土地使用权，不再承担征地补偿费或拆迂补偿费",{"key":305,"text":599,"correct":29},"搬拆补助费的标准，由各省、自治区、直辖市人民政府规定","ACE",{"id":602,"libraryId":5,"type":292,"typeLabel":293,"stem":603,"options":604,"answer":571,"analysis":33},899468,"(2013年)关于工程建设其他费中的场地准备及临时设施费，下列说法正确的有()。",[605,607,609,611,613],{"key":20,"text":606,"correct":29},"场地准备费是指为施工而进行的土地“三通一平”或“七通一平”的费用",{"key":24,"text":608,"correct":29},"其中的大型土石方工程应进入工程费中的总图运输费",{"key":27,"text":610,"correct":29},"新建项目的场地准备和临时设施费应根据实际工程重估算",{"key":31,"text":612,"correct":29},"场地准备和临时设施费=工程费用×费率+拆除清理费",{"key":305,"text":614,"correct":22},"委托施工单位修建临时设施时应计入施工单位措施费中",{"id":616,"libraryId":5,"type":292,"typeLabel":293,"stem":617,"options":618,"answer":600,"analysis":33},899469,"(2018年)下列与项目建设有关的其他费用中,属于建设管理费的有（ ）。",[619,620,622,623,625],{"key":20,"text":577,"correct":29},{"key":24,"text":621,"correct":22},"引进技术和引进设备其他费",{"key":27,"text":579,"correct":29},{"key":31,"text":624,"correct":22},"场地准备费",{"key":305,"text":626,"correct":29},"工程总承包管理费",{"id":628,"libraryId":5,"type":292,"typeLabel":293,"stem":629,"options":630,"answer":307,"analysis":33},899470,"（2019年真题）下列费用项目，属于征地补偿费的有()。",[631,633,635,637,639],{"key":20,"text":632,"correct":22},"拆迁补偿金",{"key":24,"text":634,"correct":29},"安置补助费",{"key":27,"text":636,"correct":29},"地上附着物补偿费",{"key":31,"text":638,"correct":22},"迁移补偿费",{"key":305,"text":640,"correct":29},"土地管理费",{"id":642,"libraryId":5,"type":292,"typeLabel":293,"stem":643,"options":644,"answer":600,"analysis":33},899472,"(2014年)按定额的编制程序和用途，建设工程定额可划分为（）",[645,647,649,651,653],{"key":20,"text":646,"correct":29},"施工定额",{"key":24,"text":648,"correct":22},"企业定额",{"key":27,"text":650,"correct":29},"预算定额",{"key":31,"text":652,"correct":22},"补充定额",{"key":305,"text":654,"correct":29},"投资估算指标",{"id":656,"libraryId":5,"type":292,"typeLabel":293,"stem":657,"options":658,"answer":352,"analysis":33},899473,"(2016年)关于工程量清单计价和定额计价，下列计价公式中正确的有()。",[659,661,663,665,667],{"key":20,"text":660,"correct":22},"单位工程直接费=∑（假定建筑安装产品工程量×工料单价）+措施费",{"key":24,"text":662,"correct":22},"单位工程概预算费=单位工程直接费+企业管理费+利润+税金",{"key":27,"text":664,"correct":29},"分部分项工程费=∑（分部分项工程量×分部分项工程综合单价）",{"key":31,"text":666,"correct":29},"措施项目费=∑按“项”计算的措施项目费+∑（措施项目工程量×措施项目综合单价）",{"key":305,"text":668,"correct":29},"单位工程报价=分部分项工程费+措施项目费+其他项目费+规费+税金",{"id":670,"libraryId":5,"type":292,"typeLabel":293,"stem":671,"options":672,"answer":683,"analysis":33},899474,"(2018年)关于工程量清单计价的基本程序和方法,下列说法正确的有（ ）。",[673,675,677,679,681],{"key":20,"text":674,"correct":22},"单位工程造价通过直接费、间接费、利润汇总",{"key":24,"text":676,"correct":29},"计价过程包括工程量清单的编制和应用两个阶段",{"key":27,"text":678,"correct":22},"项目特征和计量单位的确定与施工组织设计无关",{"key":31,"text":680,"correct":29},"招标文件中划分的由投标人承租的风险费用列入综合单价中",{"key":305,"text":682,"correct":22},"工程量清单计价活动伴随竣工结算而结束","BD",[685,688,691,694,697,700],{"id":15,"name":686,"category":7,"favorite":687},"领导干部任职前廉政法规知识测试题",92,{"id":689,"name":690,"category":7,"favorite":15},595,"建筑结构与设备",{"id":692,"name":693,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":695,"name":696,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":698,"name":699,"category":7,"favorite":8},534,"BIM工程师",{"id":701,"name":699,"category":7,"favorite":8},535]