[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-582-27":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":617},{"id":5,"name":6,"category":7,"favorite":8},582,"建设工程计价","建筑工程",0,27,50,2160,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,190,202,214,226,238,250,262,270,282,294,306,318,330,342,354,366,378,390,402,414,426,438,450,462,474,486,498,510,521,533,545,557,569,581,593,605],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":24,"analysis":33},899169,1,"单选题","（2017年考题）已知人工挖某土方1m3的基本工作时间为1个工作日，辅助工作时间占工序作业时间的5%，准备与结束工作时间、不可避免的中断时间、休息时间分别占工作日的3%、2%、15%，则该人工挖土的时间定额为（ ）工日\u002F10m3。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","13.33",false,{"key":24,"text":25,"correct":26},"B","13.16",true,{"key":28,"text":29,"correct":22},"C","13.13",{"key":31,"text":32,"correct":22},"D","12.50","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":31,"analysis":33},899170,"（2016年考题）若完成1m3墙体砌筑工作的基本工时为0.5工日，辅助工作时间占工序时间的4%，准备与结束工作时间、不可避免的中断时间、休息时间分别占工作时间的6%、3%和12%，该工程时间定额为（ ）工日\u002Fm3。",[38,40,42,44],{"key":20,"text":39,"correct":22},"0.581",{"key":24,"text":41,"correct":22},"0.608",{"key":28,"text":43,"correct":22},"0.629",{"key":31,"text":45,"correct":26},"0.659",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":28,"analysis":33},899171,"（2017年考题）确定施工机械台班定额消耗量前需计算机械时间利用系数，其计算公式正确的是（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"机械时间利用系数=机械纯工作1h正常生产率×工作班纯工作时间",{"key":24,"text":53,"correct":22},"机械时间利用系数=1\u002F机械台班产量定额",{"key":28,"text":55,"correct":26},"机械时间利用系数=机械在一个工作班内纯工作时间\u002F一个工作班延续时间（8h）",{"key":31,"text":57,"correct":22},"机械时间利用系数=一个工作班延续时间（8h）\u002F机械在一个工作班内纯工作时间",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":20,"analysis":33},899172,"（2017年考题）已知砌筑1m3砖墙中砖净量和损耗量分别为529块、6块，百块砖体积按0.146m3计算，砂浆损耗率为10%。则砌筑1m3砖墙的砂浆用量为（ ）m3。",[62,64,66,68],{"key":20,"text":63,"correct":26},"0.250",{"key":24,"text":65,"correct":22},"0.253",{"key":28,"text":67,"correct":22},"0.241",{"key":31,"text":69,"correct":22},"0.243",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":31,"analysis":33},899173,"（2015年考题）用水泥砂浆砌筑2m3砖墙，标准砖（240mm×115mm×53mm）的总耗用量为1113块。已知砖的损耗率为5%，则标准砖、砂浆的净用量分别为（ ）。",[74,76,78,80],{"key":20,"text":75,"correct":22},"1057块、0.372m3",{"key":24,"text":77,"correct":22},"1057块、0.454m3",{"key":28,"text":79,"correct":22},"1060块、0.372m3",{"key":31,"text":81,"correct":26},"1060块、0.449m3",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":20,"analysis":33},899174,"（2015年考题）某出料容量750L的混凝土搅拌机，每循环一次的正常延续时间为9分钟，机械正常利用系数为0.9。按8小时工作制考虑，该机械的台班产量定额为（ ）。",[86,88,90,92],{"key":20,"text":87,"correct":26},"36m3\u002F台班",{"key":24,"text":89,"correct":22},"40m3\u002F台班",{"key":28,"text":91,"correct":22},"0.28台班\u002Fm",{"key":31,"text":93,"correct":22},"0.25台班\u002Fm3",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":28,"analysis":33},899175,"（2016年考题）某出料容量750L的砂浆搅拌机，每一次循环工作中，运料、装料、搅拌、卸料、终端需要的时间分别为150s、40s、250s、50s、40s，运料和其他时间的交叠时间为50s，机械利用系数为0.8。该机械的台班产量定额为（ ）m3\u002F台班。",[98,100,102,104],{"key":20,"text":99,"correct":22},"29.79",{"key":24,"text":101,"correct":22},"32.60",{"key":28,"text":103,"correct":26},"36.00",{"key":31,"text":105,"correct":22},"39.27",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":24,"analysis":33},899176,"（2016年考题）下列机械工作时间中，属于有效工作时间的是（ ）。",[110,112,114,116],{"key":20,"text":111,"correct":22},"筑路机在工作区末端的掉头时间",{"key":24,"text":113,"correct":26},"体积达标而未达到载重吨位的货物汽车运输时间",{"key":28,"text":115,"correct":22},"机械在工作地点之间的转移时间",{"key":31,"text":117,"correct":22},"装车数量不足而在低负荷下工作的时间",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":20,"analysis":33},899177,"（2018年考题）关于材料消耗的性质及确定材料消耗量的基本方法，下列说法正确的是（ ）",[122,124,126,128],{"key":20,"text":123,"correct":26},"理论计算法适用于确定材料净用量",{"key":24,"text":125,"correct":22},"必须消耗的材料量是指材料的净用量",{"key":28,"text":127,"correct":22},"土石方爆破工程所需的炸药、雷管、引信属于非实体材料",{"key":31,"text":129,"correct":22},"现场统计法主要适用于确定材料损耗量",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":20,"analysis":33},899178,"（2018年考题）某砼输送泵每小时纯工作状态可输送砼25m3，泵的时间利用系数为0.75，则该砼输送泵的产量定额为（ ）。",[134,136,138,140],{"key":20,"text":135,"correct":26},"150m3\u002F台班",{"key":24,"text":137,"correct":22},"0.67台班\u002F100m",{"key":28,"text":139,"correct":22},"200m3\u002F台班",{"key":31,"text":141,"correct":22},"0.50台班\u002F100m3",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":28,"analysis":33},899179,"（2018年考题）已知某人工抹灰10㎡的基本工作时间为4小时，辅助工作时间占工序作业时间的5%，准备与结束工作时间、不可避免的中断时回分部占工作日的6%、11%、3%。则该人工抹灰的时间定额为（ ）工日\u002F100㎡",[146,148,150,152],{"key":20,"text":147,"correct":22},"6.3",{"key":24,"text":149,"correct":22},"6.56",{"key":28,"text":151,"correct":26},"6.58",{"key":31,"text":153,"correct":22},"6.67",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":24,"analysis":33},899180,"（2020年真题）对工人工作时间消耗的分类中属于必需消耗时间而被计入时间定额的是（）。",[158,160,162,164],{"key":20,"text":159,"correct":22},"偶然工作时间",{"key":24,"text":161,"correct":26},"工人休息时间",{"key":28,"text":163,"correct":22},"施工本身造成的停工时间",{"key":31,"text":165,"correct":22},"非施工本身造成的停工时间",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":20,"analysis":33},899181,"（2020年真题）干混地面砂浆DSM20贴600mm*600mm石材楼面，灰缝宽2mm,石材损耗率2%，每100平米需（）块。",[170,172,174,176],{"key":20,"text":171,"correct":26},"281.46",{"key":24,"text":173,"correct":22},"281.57",{"key":28,"text":175,"correct":22},"283.33",{"key":31,"text":177,"correct":22},"283.45",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":28,"analysis":33},899182,"（2020年真题）某装载容量为15m3的运输机械，每运输10km的一次循环工作中，装车、运输、卸料、空车返回时间分别为10min、15min、8min和12min，机械时间利用系数为0.75，则该机械运输10Km的台班产量定额为（ ）10m3\u002Ft。",[182,184,186,188],{"key":20,"text":183,"correct":22},"8",{"key":24,"text":185,"correct":22},"10.91",{"key":28,"text":187,"correct":26},"12",{"key":31,"text":189,"correct":22},"16.36",{"id":191,"libraryId":5,"type":15,"typeLabel":16,"stem":192,"options":193,"answer":31,"analysis":33},899183,"（2017年考题）在计算预算定额人工工日消耗量时，含在人工幅度差內的用工是（ ）。",[194,196,198,200],{"key":20,"text":195,"correct":22},"超运距用工",{"key":24,"text":197,"correct":22},"材料加工用工",{"key":28,"text":199,"correct":22},"机械土方工程的配合用工",{"key":31,"text":201,"correct":26},"工种交叉作业相互影响的停歇用工",{"id":203,"libraryId":5,"type":15,"typeLabel":16,"stem":204,"options":205,"answer":28,"analysis":33},899184,"（2017年考题）某挖掘机械挖二类土方的台班产量定额为100m3\u002F台班，当机械幅度差系数为20%时，该机械挖二类土方1000m3预算定额的台班耗用量应为（ ）台班。",[206,208,210,212],{"key":20,"text":207,"correct":22},"8.0",{"key":24,"text":209,"correct":22},"10.0",{"key":28,"text":211,"correct":26},"12.0",{"key":31,"text":213,"correct":22},"12.5",{"id":215,"libraryId":5,"type":15,"typeLabel":16,"stem":216,"options":217,"answer":31,"analysis":33},899185,"（2016年考题）下列材料损耗，应计入预算定额材料损耗量的是（ ）。",[218,220,222,224],{"key":20,"text":219,"correct":22},"场外运输损耗",{"key":24,"text":221,"correct":22},"工地仓储损耗",{"key":28,"text":223,"correct":22},"一般性检验鉴定损耗",{"key":31,"text":225,"correct":26},"施工加工损耗",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":20,"analysis":33},899186,"（2017年考题）概算定额与预算定额的差异主要表现在（ ）的不同。",[230,232,234,236],{"key":20,"text":231,"correct":26},"项目划分",{"key":24,"text":233,"correct":22},"主要工程內容",{"key":28,"text":235,"correct":22},"主要表达方式",{"key":31,"text":237,"correct":22},"基本使用方法",{"id":239,"libraryId":5,"type":15,"typeLabel":16,"stem":240,"options":241,"answer":20,"analysis":33},899187,"（2018年考题）下列工程造价信息中，最能体现市场机制下信息动态性变化特征的是（ ）。",[242,244,246,248],{"key":20,"text":243,"correct":26},"工程价格信息",{"key":24,"text":245,"correct":22},"政策性文件",{"key":28,"text":247,"correct":22},"计价标准和规范",{"key":31,"text":249,"correct":22},"工程定额",{"id":251,"libraryId":5,"type":15,"typeLabel":16,"stem":252,"options":253,"answer":20,"analysis":33},899189,"（2019年考题）工程造价指标测算中，各类造价做据的时间需求符合造价指标的时间要求。下列造价数据的时间选取符合规定的是（ ）。",[254,256,258,260],{"key":20,"text":255,"correct":26},"投资估算采用投资估算书编制完成日期",{"key":24,"text":257,"correct":22},"最高投标限价采用投标截止日期",{"key":28,"text":259,"correct":22},"合同价采用合同签订日期",{"key":31,"text":261,"correct":22},"结算价采用工程结算日期",{"id":263,"libraryId":5,"type":15,"typeLabel":16,"stem":264,"options":265,"answer":28,"analysis":33},899190,"（2019年考题）关于工程造价指数的计算，下列表达式正确的是（ ）。 A.材料费价格指数=Σ（同期各种材料单价X所有材料费用\u002F所有材料费用之和）B单位工程价格指数=Σ（同期各分部工程价格指数x各分部工程费用\u002F单位工程费用）C单项工程造价指数=报告期单项工程造价指标\u002F基期单项工程造价指标 D.建设工程造价综合指数=报告期建设工程造价综合指标\u002F基期建设工程造价综合指标.",[266,267,268,269],{"key":20,"text":20,"correct":22},{"key":24,"text":24,"correct":22},{"key":28,"text":28,"correct":26},{"key":31,"text":31,"correct":22},{"id":271,"libraryId":5,"type":15,"typeLabel":16,"stem":272,"options":273,"answer":31,"analysis":33},899191,"（2016年考题）完成某分部分项工程1m3需基本用工0.5工日，超运距用工0.05工日，辅助用工0.1工日。如人工幅度差系数为10%，则该工程预算定额人工工日消耗量为（ ）工日\u002F10m3。",[274,276,278,280],{"key":20,"text":275,"correct":22},"6.05",{"key":24,"text":277,"correct":22},"5.85",{"key":28,"text":279,"correct":22},"7.00",{"key":31,"text":281,"correct":26},"7.15",{"id":283,"libraryId":5,"type":15,"typeLabel":16,"stem":284,"options":285,"answer":20,"analysis":33},899192,"（2020年真题）关于概算定额，下列说法正确的是（ ）。",[286,288,290,292],{"key":20,"text":287,"correct":26},"不仅包括人工、材料和施工机具台班的数量标准，还包括费用标准",{"key":24,"text":289,"correct":22},"是施工定额的综合与扩大",{"key":28,"text":291,"correct":22},"反映的主要内容、项目划分和综合扩大程度与预算定额类似",{"key":31,"text":293,"correct":22},"定额水平体现平均先进水平",{"id":295,"libraryId":5,"type":15,"typeLabel":16,"stem":296,"options":297,"answer":20,"analysis":33},899193,"（2016年考题）某建筑工程报告期各项费用构成和各单项价格指数如下表所示，则该工程的建筑安装工程造价指数为（ ）。",[298,300,302,304],{"key":20,"text":299,"correct":26},"0.995",{"key":24,"text":301,"correct":22},"0.996",{"key":28,"text":303,"correct":22},"0.997",{"key":31,"text":305,"correct":22},"0.998",{"id":307,"libraryId":5,"type":15,"typeLabel":16,"stem":308,"options":309,"answer":28,"analysis":33},899194,"（2017年考题）项目决策阶段对环境治理方案进行技术经济比较时，不作为比较内容的（ ）。",[310,312,314,316],{"key":20,"text":311,"correct":22},"技术水平对比",{"key":24,"text":313,"correct":22},"管理及监测方式对比",{"key":28,"text":315,"correct":26},"安全生产条件对比",{"key":31,"text":317,"correct":22},"环境效益对比",{"id":319,"libraryId":5,"type":15,"typeLabel":16,"stem":320,"options":321,"answer":28,"analysis":33},899195,"（2015年考题）.某类建筑材料本身的价格不高，但所需的运输费用却很高，该类建筑材料的价格信息一般具有较明显的（ ）。",[322,324,326,328],{"key":20,"text":323,"correct":22},"专业性",{"key":24,"text":325,"correct":22},"季节性",{"key":28,"text":327,"correct":26},"区域性",{"key":31,"text":329,"correct":22},"动态性",{"id":331,"libraryId":5,"type":15,"typeLabel":16,"stem":332,"options":333,"answer":28,"analysis":33},899196,"（2015年考题）某工程项目报告期需采购设备甲2台，设备乙1台。报告期、基期设备价格如下表所示，该工程报告期的设备价格指数为（ ）。",[334,336,338,340],{"key":20,"text":335,"correct":22},"1.00",{"key":24,"text":337,"correct":22},"1.13",{"key":28,"text":339,"correct":26},"1.20",{"key":31,"text":341,"correct":22},"1.40",{"id":343,"libraryId":5,"type":15,"typeLabel":16,"stem":344,"options":345,"answer":20,"analysis":33},899197,"（2016年考题）下列工程造价指数，既属于总指数又可用综合指数形式表示的是（ ）。",[346,348,350,352],{"key":20,"text":347,"correct":26},"设备、工器具价格指数",{"key":24,"text":349,"correct":22},"建筑安装工程造价指数",{"key":28,"text":351,"correct":22},"单项工程造价指数",{"key":31,"text":353,"correct":22},"建设项目造价指数",{"id":355,"libraryId":5,"type":15,"typeLabel":16,"stem":356,"options":357,"answer":24,"analysis":33},899198,"（2017年考题）“工程造价信息应针对不同层次管理者的要求进行适当加工，针对不同管理层提供不同要求和浓缩程度的信息。”这体现了工程造价信息管理应遵循的（ ）原则。",[358,360,362,364],{"key":20,"text":359,"correct":22},"标准化",{"key":24,"text":361,"correct":26},"有效性",{"key":28,"text":363,"correct":22},"定量化",{"key":31,"text":365,"correct":22},"高效处理",{"id":367,"libraryId":5,"type":15,"typeLabel":16,"stem":368,"options":369,"answer":31,"analysis":33},899199,"（2020年真题）关于工程造价指标，下列说法正确的是（）。",[370,372,374,376],{"key":20,"text":371,"correct":22},"按照工程构成不同，工程造价指标可划分为人工指标、材料指标、机械台班指标",{"key":24,"text":373,"correct":22},"工程造价指标测算时，部分数据可通过理论推测获得",{"key":28,"text":375,"correct":22},"造价指标可分行业、分专业进行测算，不受区域范围影响",{"key":31,"text":377,"correct":26},"汇总计算法计算工程造价指标时，应采用加权平均的方法",{"id":379,"libraryId":5,"type":15,"typeLabel":16,"stem":380,"options":381,"answer":20,"analysis":33},899200,"（2020年真题）2020年某水泥厂建设工程的建筑安装工程造价为7.31亿元。其中:矿山工程造价为7800万元，定额编制期同类项目的矿山工程造价为6000万元。该水泥厂建设工程造价综合指数为1.20，则该矿山工程的造价指数是（）。",[382,384,386,388],{"key":20,"text":383,"correct":26},"1.30",{"key":24,"text":385,"correct":22},"0.77",{"key":28,"text":387,"correct":22},"0.92",{"key":31,"text":389,"correct":22},"1.56",{"id":391,"libraryId":5,"type":15,"typeLabel":16,"stem":392,"options":393,"answer":28,"analysis":33},899201,"（2017年考题）其挖掘机配司机1人，若年制度工作日为245天，年工作台班为220台班，人工工日单价为80元，则该挖掘机的人工费为（ ）元\u002F台班。",[394,396,398,400],{"key":20,"text":395,"correct":22},"71.8",{"key":24,"text":397,"correct":22},"80.0",{"key":28,"text":399,"correct":26},"89.1",{"key":31,"text":401,"correct":22},"132.7",{"id":403,"libraryId":5,"type":15,"typeLabel":16,"stem":404,"options":405,"answer":28,"analysis":33},899202,"（2018年考题）某材料原价为300元\u002Ft，运杂费及运输损耗费台计为50元\u002Ft，采购及保管费费率3%，则该材料预算单价为（ ）元\u002Ft。",[406,408,410,412],{"key":20,"text":407,"correct":22},"350.0",{"key":24,"text":409,"correct":22},"359.0",{"key":28,"text":411,"correct":26},"360.5",{"key":31,"text":413,"correct":22},"360.8",{"id":415,"libraryId":5,"type":15,"typeLabel":16,"stem":416,"options":417,"answer":24,"analysis":33},899203,"（2018年考题）关于施工机械台班单价的确定，下列表述式正确的是（ ）。",[418,420,422,424],{"key":20,"text":419,"correct":22},"台班折旧费=机械原值x（1-残值率）\u002F耐用总台班",{"key":24,"text":421,"correct":26},"耐用总台班=检修间隔台班x（检修次数+1）",{"key":28,"text":423,"correct":22},"台班检修费=一次检修费x检修次数\u002F耐用总台班",{"key":31,"text":425,"correct":22},"台班维护费=Σ（各级维护一次费用x各级维护次数）\u002F耐用总台班",{"id":427,"libraryId":5,"type":15,"typeLabel":16,"stem":428,"options":429,"answer":24,"analysis":33},899204,"（2016年考题）从甲、乙两地采购某工程材料，采购量及有关费用如下表所示，该工程材料的材料单价为（ ）元\u002Ft。",[430,432,434,436],{"key":20,"text":431,"correct":22},"262.08",{"key":24,"text":433,"correct":26},"262.16",{"key":28,"text":435,"correct":22},"262.42",{"key":31,"text":437,"correct":22},"262.50",{"id":439,"libraryId":5,"type":15,"typeLabel":16,"stem":440,"options":441,"answer":28,"analysis":33},899205,"（2019年考题）某工程采用两票制支付方式采购某种材料，已知材料原价和运杂费的含税价格分别为500元\u002Ft、30元\u002Ft，材料运输损耗率采购及保管费率分别为0.5%、3.5%，材料采购和运输的增值税率分别为13%、9%，则该材料的不含税单价为（ ）元？",[442,444,446,448],{"key":20,"text":443,"correct":22},"480.87",{"key":24,"text":445,"correct":22},"481.47",{"key":28,"text":447,"correct":26},"488.88",{"key":31,"text":449,"correct":22},"489.49",{"id":451,"libraryId":5,"type":15,"typeLabel":16,"stem":452,"options":453,"answer":31,"analysis":33},899206,"（2019年考题）下列用项目中属于施工仪器仪表台班单价构成内容的是（ ）。",[454,456,458,460],{"key":20,"text":455,"correct":22},"人工费",{"key":24,"text":457,"correct":22},"燃料费",{"key":28,"text":459,"correct":22},"检测软件费",{"key":31,"text":461,"correct":26},"校验费",{"id":463,"libraryId":5,"type":15,"typeLabel":16,"stem":464,"options":465,"answer":31,"analysis":33},899207,"（2015年考题）某大型施工机械需配机上司机、机上操作人员各一名，若年制度工作日为250天，年工作台班为200台班，人工日工资单价均为100元\u002F工日，则该施工机械的台班人工费为（ ）元\u002F台班。",[466,468,470,472],{"key":20,"text":467,"correct":22},"100",{"key":24,"text":469,"correct":22},"125",{"key":28,"text":471,"correct":22},"200",{"key":31,"text":473,"correct":26},"250",{"id":475,"libraryId":5,"type":15,"typeLabel":16,"stem":476,"options":477,"answer":24,"analysis":33},899208,"（2015年考题）某工地商品混凝土分别从甲、乙两地采购，甲地采购量及材料单价分别为400m3、350元\u002Fm3，乙地采购量及有关费用如下表所示。则该工地商品混凝土的材料单价应为（ ）元\u002Fm3。",[478,480,482,484],{"key":20,"text":479,"correct":22},"341.00",{"key":24,"text":481,"correct":26},"341.68",{"key":28,"text":483,"correct":22},"342.50",{"key":31,"text":485,"correct":22},"343.06",{"id":487,"libraryId":5,"type":15,"typeLabel":16,"stem":488,"options":489,"answer":20,"analysis":33},899209,"（2016年考题）某大型施工机械预算价格为5万元，机械耐用总台班为1250台班，大修理周期数为4，一次大修理费用为2000元，经常修理费系数为60%，机上人工费和燃料动力费为60元\u002F台班。不考虑残值和其他有关费用，则该机械台班单价为（ ）元\u002F台班。",[490,492,494,496],{"key":20,"text":491,"correct":26},"107.68",{"key":24,"text":493,"correct":22},"110.24",{"key":28,"text":495,"correct":22},"112.80",{"key":31,"text":497,"correct":22},"52.80",{"id":499,"libraryId":5,"type":15,"typeLabel":16,"stem":500,"options":501,"answer":20,"analysis":33},899210,"（2017年考题）关于材料单价的计算，下列计算公式中正确的是（ ）。",[502,504,506,508],{"key":20,"text":503,"correct":26},"（供应价格+运杂费）×（1+运输损耗率）×（1+采购及保管费率）",{"key":24,"text":505,"correct":22},"（供应价格+运杂费）\u002F[（1+运输损耗率）×（1+采购及保管费率）]",{"key":28,"text":507,"correct":22},"（供应价格+运杂费）×（1+采购及保管费率）\u002F（1+采购及保管费率）",{"key":31,"text":509,"correct":22},"（供应价格+运杂费）×（1+运输损耗率）\u002F（1+采购及保管费率）",{"id":511,"libraryId":5,"type":15,"typeLabel":16,"stem":512,"options":513,"answer":28,"analysis":33},899211,"（2019年考题）编制预算定额人工日消耗量时，实际工程现场运距超过预算定额取定运距时的用工应计入（ ）。",[514,515,517,519],{"key":20,"text":195,"correct":22},{"key":24,"text":516,"correct":22},"辅助用工",{"key":28,"text":518,"correct":26},"二次搬运用工",{"key":31,"text":520,"correct":22},"人工幅度差",{"id":522,"libraryId":5,"type":15,"typeLabel":16,"stem":523,"options":524,"answer":28,"analysis":33},899212,"（2020年真题）采用\"一票制\"、“二票制\"支付方式采购材料的，在进行增值税进项税抵扣的，正确的做法是（）。",[525,527,529,531],{"key":20,"text":526,"correct":22},"\"一票制\"下，构成材料价格的所有费用均按货物销售适用的税率进行抵扣",{"key":24,"text":528,"correct":22},"“一票制\"下，材料原价按货物销售适用税率进行抵扣，运杂费不再进行抵扣",{"key":28,"text":530,"correct":26},"\"二票制\"下，材料原价按货物销售适用税率、运杂费按交通运输适用税率进",{"key":31,"text":532,"correct":22},"\"二票制\"下，材料原价按货物销售适用税率，运杂费、运输损耗和采购保",{"id":534,"libraryId":5,"type":15,"typeLabel":16,"stem":535,"options":536,"answer":20,"analysis":33},899213,"（2020年真题）一台设备原值5万元，使用期内大修3次，每维修期运转400台班，设备残值5%。该设备台班折旧费为（）",[537,539,541,543],{"key":20,"text":538,"correct":26},"29.69",{"key":24,"text":540,"correct":22},"31.25",{"key":28,"text":542,"correct":22},"39.58",{"key":31,"text":544,"correct":22},"41.67",{"id":546,"libraryId":5,"type":15,"typeLabel":16,"stem":547,"options":548,"answer":31,"analysis":33},899214,"（2016年考题）建设项目投资决策阶段，在技术方案中选择生产方法时应重点关注（ ）。",[549,551,553,555],{"key":20,"text":550,"correct":22},"是否选择了合理的物料消耗定额",{"key":24,"text":552,"correct":22},"是否符合工艺流程的柔性安排",{"key":28,"text":554,"correct":22},"是否使工艺流程中的工序合理衔接",{"key":31,"text":556,"correct":26},"是否符合节能清洁要求",{"id":558,"libraryId":5,"type":15,"typeLabel":16,"stem":559,"options":560,"answer":31,"analysis":33},899215,"（2017年考题）关于项目投资估算的作用，下列说法中正确的是（ ）。",[561,563,565,567],{"key":20,"text":562,"correct":22},"项目建议书阶段的投资估算，是确定建设投资最高限额的依据",{"key":24,"text":564,"correct":22},"可行性研究阶段的授资估算，是项目投资决策的重要依据，不得突破",{"key":28,"text":566,"correct":22},"投资估算不能作为制定建设货款计划的依据",{"key":31,"text":568,"correct":26},"投资估算是核算建设项目固定资产需要数的重要依据",{"id":570,"libraryId":5,"type":15,"typeLabel":16,"stem":571,"options":572,"answer":28,"analysis":33},899216,"（2017年考题）关于我国项目前期阶段投资估算的精度要求下列说法中正确的是（ ）。",[573,575,577,579],{"key":20,"text":574,"correct":22},"项目建议书阶段，允许误差大于±30%",{"key":24,"text":576,"correct":22},"投资设想阶段，要求误差控制在±30%以內",{"key":28,"text":578,"correct":26},"预可行性研究阶段，要求误差控制在±20%以內",{"key":31,"text":580,"correct":22},"可行性研究阶段，要求误差控制在±15%以內",{"id":582,"libraryId":5,"type":15,"typeLabel":16,"stem":583,"options":584,"answer":28,"analysis":33},899217,"（2015年考题）投资估算的主要工作包括：①估算预备费②估算工程建设其他费③估算工程费用④估算设备购置费。其正确的工作步骤是（ ）。",[585,587,589,591],{"key":20,"text":586,"correct":22},"③④②①",{"key":24,"text":588,"correct":22},"③④①②",{"key":28,"text":590,"correct":26},"④③②①",{"key":31,"text":592,"correct":22},"④③①②",{"id":594,"libraryId":5,"type":15,"typeLabel":16,"stem":595,"options":596,"answer":24,"analysis":33},899218,"（2016年考题）下列安装工程费估算公式中，适用于估算工业炉窑砌筑和工艺保温或绝热工程安装工程费的是（ ）。",[597,599,601,603],{"key":20,"text":598,"correct":22},"设备原价×设备安装费率（%）",{"key":24,"text":600,"correct":26},"重量（体积、面积）总量×单位重量（体积、面积）安装费指标",{"key":28,"text":602,"correct":22},"设备原价×材料费占设备费百分比×材料安装费率（%）",{"key":31,"text":604,"correct":22},"安装工程功能总量×功能单位安装工程费指标",{"id":606,"libraryId":5,"type":15,"typeLabel":16,"stem":607,"options":608,"answer":28,"analysis":33},899219,"（2016年考题）按照形成资产法编制建设项目投资估算表，下列费用中可计入股东资产其他费用的是（ ）。",[609,611,613,615],{"key":20,"text":610,"correct":22},"开办费",{"key":24,"text":612,"correct":22},"非专利技术使用费",{"key":28,"text":614,"correct":26},"土地使用权取得费",{"key":31,"text":616,"correct":22},"生产准备费",[618,621,624,627,630,633],{"id":15,"name":619,"category":7,"favorite":620},"领导干部任职前廉政法规知识测试题",92,{"id":622,"name":623,"category":7,"favorite":15},595,"建筑结构与设备",{"id":625,"name":626,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":628,"name":629,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":631,"name":632,"category":7,"favorite":8},534,"BIM工程师",{"id":634,"name":632,"category":7,"favorite":8},535]