[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-582-23":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":615},{"id":5,"name":6,"category":7,"favorite":8},582,"建设工程计价","建筑工程",0,23,50,2160,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,190,202,214,226,238,250,261,273,285,297,309,321,333,345,357,369,381,392,403,415,427,439,451,463,475,487,499,511,521,533,543,555,567,579,591,603],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":24,"analysis":33},898967,1,"单选题","某建设项目业主与施工单位签订了可调价格合同。合同中约定：主导施工机械一台为施工单位自有设备，台班单价900元／台班，折旧费为150元／台班，人工日工资单价为40元／工日，窝工工费10元／工日，以人工费为基数的综合费率为30％。合同履行中，因场外停电全场停工2天，造成人员窝工20个工日；因业主指令增加一项新工作，完成该工作需要5天时间，机械5台班，人工20个工日，材料费5500元，则施工单位可向业主提出索赔额为()元。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","11300",false,{"key":24,"text":25,"correct":26},"B","11540",true,{"key":28,"text":29,"correct":22},"C","13880",{"key":31,"text":32,"correct":22},"D","11600","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},898968,"在下列需签证的事件中，需要由发包人以书面形式向承包人发出指令的是()。",[38,40,42,44],{"key":20,"text":39,"correct":26},"完成合同以外的零星项目",{"key":24,"text":41,"correct":22},"因场地条件导致合同工程内容不一致",{"key":28,"text":43,"correct":22},"因地质条件导致合同工程内容不一致",{"key":31,"text":45,"correct":22},"因水文条件导致合同工程内容不一致",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":20,"analysis":33},898969,"对于不实行招标的建设工程，因法律法规政策变化引起合同价款调整的，调价基准日期一般为（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":26},"施工合同签订前的第28天",{"key":24,"text":53,"correct":22},"提交投标文件的截止时间前的第28天",{"key":28,"text":55,"correct":22},"施工合同签订前的第56天",{"key":31,"text":57,"correct":22},"提交投标文件截止时间前的第56天",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":20,"analysis":33},898970,"施工合同履行期间，关于计日工费用的处理，下列说法中正确的是（ ）。",[62,64,66,68],{"key":20,"text":63,"correct":26},"已标价工程量清单中无某项计日工单价时，应按工程变更有关规定商定计日工单价",{"key":24,"text":65,"correct":22},"承包人通知发包人以计日工方式实施的零星工作，双方应按计日工方式予以结算",{"key":28,"text":67,"correct":22},"现场签证的计日工数量与招标工程量清单中所列不同时，应按工程变更有关规定进行价款调整",{"key":31,"text":69,"correct":22},"施工各期间发生的计日工费用应在竣工结算时一并支付",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":20,"analysis":33},898971,"每个支付期末，承包人应与进度款同期向发包人提交本期间所有（ ）记录的签证汇总表，以说明本期间自己认为有权得到的相应金额。",[74,76,78,80],{"key":20,"text":75,"correct":26},"计日工",{"key":24,"text":77,"correct":22},"暂估价",{"key":28,"text":79,"correct":22},"暂列金额",{"key":31,"text":81,"correct":22},"总承包服务费",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":28,"analysis":33},898972,"根据《标准施工招标文件》(2007年版)，下列事件中，既可索赔工期又可索赔费用的是()。",[86,88,90,92],{"key":20,"text":87,"correct":22},"承包人提前竣工",{"key":24,"text":89,"correct":22},"提前向承包人提供工程设备",{"key":28,"text":91,"correct":26},"施工中遇到不利物质条件",{"key":31,"text":93,"correct":22},"异常恶劣的气候条件导致工期延误",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":28,"analysis":33},898973,"某工程合同实施过程中发生了变更事件，在已标价清单中没有适用也没有类似单价，且工程造价管理机构发布的信息价格也缺价，承包人根据变更工程资料、计量规则、计价办法和有合法依据的市场价格计算出变更工程项目的价格为10万元，已知该项目发承包阶段招标控制价为1000万元，中标价为900万元(招标控制价和中标价中均包含20万元的安全文明施工费)，则该变更工程项目确认的变更价格应为()万元。",[98,100,102,104],{"key":20,"text":99,"correct":22},"9.00",{"key":24,"text":101,"correct":22},"8.98",{"key":28,"text":103,"correct":26},"10.00",{"key":31,"text":105,"correct":22},"9.80",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":28,"analysis":33},898974,"某工程合同价格为5000万元，计划工期是200天，施工期间因非承包人原因导致工期延误10天，若同期该公司承揽的所有工程合同总价为2.5亿元，计划总部管理费为1250万元，则承包人可以索赔的总部管理费为()万元。",[110,112,114,116],{"key":20,"text":111,"correct":22},"7.5",{"key":24,"text":113,"correct":22},"10",{"key":28,"text":115,"correct":26},"12.5",{"key":31,"text":117,"correct":22},"15",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":28,"analysis":33},898975,"若在某工程施工过程中发生以下事件：5月1日～5月15日因发包人原因而延误，5月5日～5月25日因客观原因而延误，5月13日~5月22日因承包人原因而延误，则在5月13日～5月15日时间段内承包人可以获得的补偿是()。",[122,124,126,128],{"key":20,"text":123,"correct":22},"工期补偿",{"key":24,"text":125,"correct":22},"费用补偿",{"key":28,"text":127,"correct":26},"工期+费用补偿",{"key":31,"text":129,"correct":22},"没有补偿",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":31,"analysis":33},898976,"某工程施工合同约定采用价格指数法调整合同价款，各项费用权重及价格如下表所示。已知该工程9月份完成的工程合同价款为3000万元，则9月份合同价款调整金额为()万元。",[134,136,138,140],{"key":20,"text":135,"correct":22},"22.5",{"key":24,"text":137,"correct":22},"61.46",{"key":28,"text":139,"correct":22},"75",{"key":31,"text":141,"correct":26},"97.5",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":28,"analysis":33},898977,"根据《工程工程量清单计划规范》GB50500--2013，下列关于计日工的说法中正确的是（ ）。",[146,148,150,152],{"key":20,"text":147,"correct":22},"招标工程量清单计日工数量为暂定，计日工费不计入投标总价",{"key":24,"text":149,"correct":22},"发包人通知承包人以计日工方式实施的零星工作，承包人可以视情况决定是否执行",{"key":28,"text":151,"correct":26},"计日工表的费用项目包括人工费、材料费、施工机械使用费、企业管理费和利润",{"key":31,"text":153,"correct":22},"计日工金额不列入期中支付，在竣工结算时一并支付",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":31,"analysis":33},898978,"由于发包人的原因使工程未在约定的时间内竣工的，对原约定竣工日期后继续施工的工程进行价格调整时，涉及原约定竣工日期价格指数与实际竣工日期价格指数，则调整价格差额计算应采用()。",[158,160,162,164],{"key":20,"text":159,"correct":22},"原约定日期的价格指数",{"key":24,"text":161,"correct":22},"实际竣工日期的价格指数",{"key":28,"text":163,"correct":22},"原约定日期的价格指数与实际竣工日期的价格指数的平均值",{"key":31,"text":165,"correct":26},"原约定日期的价格指数与实际竣工日期的价格指数中较高的一个",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":28,"analysis":33},898979,"某承包工程总价为500万元，其中材料费占45％，该工程计划工期为500天，材料储备定额天数为60天，则应支付预付款（ ）万元。",[170,172,174,176],{"key":20,"text":171,"correct":22},"36.99",{"key":24,"text":173,"correct":22},"225",{"key":28,"text":175,"correct":26},"27",{"key":31,"text":177,"correct":22},"60",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":24,"analysis":33},898980,"关于工程计量的方法，下列说法正确的是（ ）。",[182,184,186,188],{"key":20,"text":183,"correct":22},"按照合同文件中规定的工程量予以计量",{"key":24,"text":185,"correct":26},"不符合合同文件要求的工程不予计量",{"key":28,"text":187,"correct":22},"单价合同工程量必须按现行定额规定的工程量计算规则计量",{"key":31,"text":189,"correct":22},"总价合同项目的工程量是予以计量的最终工程量",{"id":191,"libraryId":5,"type":15,"typeLabel":16,"stem":192,"options":193,"answer":20,"analysis":33},898981,"有关建设工程缺陷责任期的概念和期限，下列表述中正确的是（ ）。",[194,196,198,200],{"key":20,"text":195,"correct":26},"缺陷责任期从工程通过竣工验收之日起计",{"key":24,"text":197,"correct":22},"缺陷责任期可以是36个月、12个月或24个月",{"key":28,"text":199,"correct":22},"缺陷责任期的年限应遵从《建设工程质量管理条例》的规定",{"key":31,"text":201,"correct":22},"缺陷责任期是指在正常使用条件下，建设工程的最低保修期限",{"id":203,"libraryId":5,"type":15,"typeLabel":16,"stem":204,"options":205,"answer":31,"analysis":33},898982,"关于建设项目竣工结清阶段承包人索赔的权利和期限，下列说法中正确的是（ ）。",[206,208,210,212],{"key":20,"text":207,"correct":22},"承包人接受竣工结算支付证书后再物权提出任何索赔",{"key":24,"text":209,"correct":22},"承包人只能提出工程接收证书颁发前的索赔",{"key":28,"text":211,"correct":22},"承包人提出索赔的期限自缺陷责任期满时终止",{"key":31,"text":213,"correct":26},"承包人提出索赔的期限自接受最终支付证书终止",{"id":215,"libraryId":5,"type":15,"typeLabel":16,"stem":216,"options":217,"answer":20,"analysis":33},898983,"社会投资项目采用预留保证金方式的，发承包双方可以约定将保证金交由（ ）托管。",[218,220,222,224],{"key":20,"text":219,"correct":26},"金融机构",{"key":24,"text":221,"correct":22},"发包人",{"key":28,"text":223,"correct":22},"财政部",{"key":31,"text":225,"correct":22},"政府部门",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":31,"analysis":33},898984,"发包人未按照规定的程序支付竣工结算款的，承包人正确的做法是（ ）。",[230,232,234,236],{"key":20,"text":231,"correct":22},"将该工程自主拍卖",{"key":24,"text":233,"correct":22},"将该工程折价出售",{"key":28,"text":235,"correct":22},"将该工程抵押贷款",{"key":31,"text":237,"correct":26},"催告发包人支付，并索要延迟付",{"id":239,"libraryId":5,"type":15,"typeLabel":16,"stem":240,"options":241,"answer":31,"analysis":33},898985,"建设工程在缺陷责任期内，由第三方原因造成的缺陷（ ）。",[242,244,246,248],{"key":20,"text":243,"correct":22},"应由承包人负责维修，费用从质量保证金中扣除",{"key":24,"text":245,"correct":22},"应由承包人负责维修，费用由发包人承担",{"key":28,"text":247,"correct":22},"发包人委托承包人维修的，费用由第三方支付",{"key":31,"text":249,"correct":26},"发包人委托承包人维修的，费用由发包人支付",{"id":251,"libraryId":5,"type":15,"typeLabel":16,"stem":252,"options":253,"answer":31,"analysis":33},898986,"当承发包双方的合同价款纠纷提交仲裁时，如果仲裁是在仲裁机构要求停止施工的情况下进行，承包人应对合同工程采取保护措施，由此增加的费用由（ ）承担。",[254,255,257,259],{"key":20,"text":221,"correct":22},{"key":24,"text":256,"correct":22},"承包人",{"key":28,"text":258,"correct":22},"发包人和承包人",{"key":31,"text":260,"correct":26},"败诉方",{"id":262,"libraryId":5,"type":15,"typeLabel":16,"stem":263,"options":264,"answer":24,"analysis":33},898987,"对于办理有质量争议工程的竣工结算，下列说法中错误的是（ ）。",[265,267,269,271],{"key":20,"text":266,"correct":22},"已竣工未验收但实际投入使用工程的质量争议按工程保修合同执行，竣工结算按合同约定办理",{"key":24,"text":268,"correct":26},"已竣工未投入使用工程的质量争议按工程保修合同执行，竣工结算按合同约定办理",{"key":28,"text":270,"correct":22},"停工、停建工程的质量争议可在执行工程质量监督机构处理决定后办理竣工结算",{"key":31,"text":272,"correct":22},"已竣工未验收并且未实际投入使用，其无质量争议部分的工程，竣工结算按合同约定办理",{"id":274,"libraryId":5,"type":15,"typeLabel":16,"stem":275,"options":276,"answer":28,"analysis":33},898988,"某工程施工合同对工程款付款时间约定不明，工程尚未交付、工程价款也未结算，现承包人起诉，发包人工程欠款的利息应从（ ）之日计付。",[277,279,281,283],{"key":20,"text":278,"correct":22},"工程计划交付",{"key":24,"text":280,"correct":22},"提交竣工结算文件",{"key":28,"text":282,"correct":26},"当事人起诉",{"key":31,"text":284,"correct":22},"监理工程师暂定付款",{"id":286,"libraryId":5,"type":15,"typeLabel":16,"stem":287,"options":288,"answer":20,"analysis":33},898989,"工程预付款起扣点表示（ ）。",[289,291,293,295],{"key":20,"text":290,"correct":26},"未施工工程尚需的主要材料及构件的价值相当于工程预付款数额",{"key":24,"text":292,"correct":22},"已施工工程尚需的主要材料及构件的价值相当于工程预付款数额",{"key":28,"text":294,"correct":22},"未施工工程尚需工程款相当于预付款数额",{"key":31,"text":296,"correct":22},"已施工工程尚需工程款相当于预付款数额",{"id":298,"libraryId":5,"type":15,"typeLabel":16,"stem":299,"options":300,"answer":28,"analysis":33},898990,"承包人可根据确定的工程计量结果向发包人提出支付工程进度款申请，发包人应在14天内支付最高限额为（ ）的工程价款作为工程进度款，",[301,303,305,307],{"key":20,"text":302,"correct":22},"70%",{"key":24,"text":304,"correct":22},"80%",{"key":28,"text":306,"correct":26},"90%",{"key":31,"text":308,"correct":22},"100%",{"id":310,"libraryId":5,"type":15,"typeLabel":16,"stem":311,"options":312,"answer":20,"analysis":33},898991,"由发包人提供的工程材料、工程设备的金额，应在合同价款的期中支付和结算中予以扣除，具体的扣除标准是（ ）。",[313,315,317,319],{"key":20,"text":314,"correct":26},"按签约单价和签约数量",{"key":24,"text":316,"correct":22},"按实际采购单价和实际数量",{"key":28,"text":318,"correct":22},"按签约单价和实际数量",{"key":31,"text":320,"correct":22},"按实际采购单价和签约数量",{"id":322,"libraryId":5,"type":15,"typeLabel":16,"stem":323,"options":324,"answer":20,"analysis":33},898992,"下列承包商发生的行为中，发包人可以请求解除施工合同，应予支持的是（ ）。",[325,327,329,331],{"key":20,"text":326,"correct":26},"明确表示或者以行为表明不履行合同主要义务的",{"key":24,"text":328,"correct":22},"合同约定的期限内没有完工",{"key":28,"text":330,"correct":22},"已经完成的建设工程质量不合格",{"key":31,"text":332,"correct":22},"将承包的建设工程分包的",{"id":334,"libraryId":5,"type":15,"typeLabel":16,"stem":335,"options":336,"answer":31,"analysis":33},898993,"建设工程已实际交付，但施工合同没有约定付款时间，则拖欠工程款利息的起算日期为（ ）。",[337,339,341,343],{"key":20,"text":338,"correct":22},"提交竣工结算文件之日",{"key":24,"text":340,"correct":22},"确认竣工结算文件之日",{"key":28,"text":342,"correct":22},"竣工验收合格之日",{"key":31,"text":344,"correct":26},"工程实际交付之日",{"id":346,"libraryId":5,"type":15,"typeLabel":16,"stem":347,"options":348,"answer":31,"analysis":33},898994,"施工合同价款纠纷处理中，一方当事人拒不履行，另一方当事人可以请求人民法院执行的文书是（ ）。",[349,351,353,355],{"key":20,"text":350,"correct":22},"和解协议书",{"key":24,"text":352,"correct":22},"造价认定书",{"key":28,"text":354,"correct":22},"行政调解书",{"key":31,"text":356,"correct":26},"仲裁调解书",{"id":358,"libraryId":5,"type":15,"typeLabel":16,"stem":359,"options":360,"answer":28,"analysis":33},898995,"根据《建设工程工程量清单计价规范》GB50500-2013，关于工程预付款的支付和扣回，下列说法中正确的是（ ）。",[361,363,365,367],{"key":20,"text":362,"correct":22},"预付款的比例原则上不低于合同金额的10%，不高于合同金额的20%",{"key":24,"text":364,"correct":22},"从已施工工程的主要材料及构件的价值相当于工程预付款数额时起扣",{"key":28,"text":366,"correct":26},"原已支付预付款的扣回，抵扣方式应当由双方当事人在合同中明确约定",{"key":31,"text":368,"correct":22},"发包人应在预付款扣完后14天内一次性将全额预付款保函退还给承包人",{"id":370,"libraryId":5,"type":15,"typeLabel":16,"stem":371,"options":372,"answer":28,"analysis":33},898996,"已知某建筑工程施工合同总额为8000万元，工程预付款按合同金额的20%计取，主要材料及构件造价占合同额50%。预付款起扣点为（ ）万元。",[373,375,377,379],{"key":20,"text":374,"correct":22},"1600",{"key":24,"text":376,"correct":22},"4000",{"key":28,"text":378,"correct":26},"4800",{"key":31,"text":380,"correct":22},"6400",{"id":382,"libraryId":5,"type":15,"typeLabel":16,"stem":383,"options":384,"answer":31,"analysis":33},898997,"发包人应当在核实后（ ）天内将质量保证金返还承包人。",[385,387,388,390],{"key":20,"text":386,"correct":22},"5",{"key":24,"text":117,"correct":22},{"key":28,"text":389,"correct":22},"7",{"key":31,"text":391,"correct":26},"14",{"id":393,"libraryId":5,"type":15,"typeLabel":16,"stem":394,"options":395,"answer":20,"analysis":33},898998,"缺陷责任期一般为（ ）年。",[396,398,400,402],{"key":20,"text":397,"correct":26},"1",{"key":24,"text":399,"correct":22},"2",{"key":28,"text":401,"correct":22},"3",{"key":31,"text":386,"correct":22},{"id":404,"libraryId":5,"type":15,"typeLabel":16,"stem":405,"options":406,"answer":24,"analysis":33},898999,"关于建设工程施工合同价款纠纷的处理，下列说法中正确的是（ ）。",[407,409,411,413],{"key":20,"text":408,"correct":22},"竣工验收不合格，经承包人修复后合格的，承包人支付修复费用的要求应予支持",{"key":24,"text":410,"correct":26},"竣工验收不合格，经承包人修复后合格的，修复费用应由承包人承担",{"key":28,"text":412,"correct":22},"竣工验收不合格，多次修复后仍不合格的，发包人应酌情给予承包人部分修复费用",{"key":31,"text":414,"correct":22},"安装后发现甲供设备存在质量问题，但承包人参与进场验收的，发包人不应支付承包人设备拆除、重新安装的费用",{"id":416,"libraryId":5,"type":15,"typeLabel":16,"stem":417,"options":418,"answer":28,"analysis":33},899000,"下列关于缺陷责任期的描述，说法正确的是（ ）。",[419,421,423,425],{"key":20,"text":420,"correct":22},"缺陷责任期的期限应当按照保证建筑物合理寿命期内正常使用的原则确定",{"key":24,"text":422,"correct":22},"缺陷责任期自提交竣工验收报告之日起计算",{"key":28,"text":424,"correct":26},"缺陷责任期实质上就是指预留质保金的一个期限",{"key":31,"text":426,"correct":22},"缺陷责任期自颁发工程接收证书起计算",{"id":428,"libraryId":5,"type":15,"typeLabel":16,"stem":429,"options":430,"answer":31,"analysis":33},899001,"关于建筑安装工程结算的编制，下列说法中正确的是（ ）。",[431,433,435,437],{"key":20,"text":432,"correct":22},"采用固定总价合同的，暂列金额不得调整",{"key":24,"text":434,"correct":22},"采用固定总价合同的，税率可不按政府部门新公布的税率调整",{"key":28,"text":436,"correct":22},"规费应按县级建设主管部门规定的费率计算",{"key":31,"text":438,"correct":26},"现场签证费用应依据发承包双方签证资料确认的金额计算",{"id":440,"libraryId":5,"type":15,"typeLabel":16,"stem":441,"options":442,"answer":31,"analysis":33},899002,"根据《建设工程工程量清单计价规范》（GB50500——2013），发包人应在工程开工后的28天内预付不低于当年施工进度计划的安全文明施工费总额的（ ）。",[443,445,447,449],{"key":20,"text":444,"correct":22},"30%",{"key":24,"text":446,"correct":22},"40%",{"key":28,"text":448,"correct":22},"50%",{"key":31,"text":450,"correct":26},"60%",{"id":452,"libraryId":5,"type":15,"typeLabel":16,"stem":453,"options":454,"answer":24,"analysis":33},899003,"在缺陷责任期内，下列缺陷或事故，应由承包人承担保修费用的是（ ）。",[455,457,459,461],{"key":20,"text":456,"correct":22},"发包人指定的分包人造成的质量缺陷",{"key":24,"text":458,"correct":26},"由承包人采购的建筑构配件不符合质量要求",{"key":28,"text":460,"correct":22},"使用人使用不当造成的损坏",{"key":31,"text":462,"correct":22},"不可抗力造成的质量缺陷",{"id":464,"libraryId":5,"type":15,"typeLabel":16,"stem":465,"options":466,"answer":20,"analysis":33},899004,"根据最高人民法院有关司法解释，下列不予支持的诉讼请求是（ ）。",[467,469,471,473],{"key":20,"text":468,"correct":26},"垫资工程款利息没有约定的情况下，承包人请求支付利息",{"key":24,"text":470,"correct":22},"施工合同无效，但工程竣工验收合格，承包人请求参照合同约定支付工程款",{"key":28,"text":472,"correct":22},"施工合同无效，已完工程质量合格，承包人请求参照合同约定支付工程价款",{"key":31,"text":474,"correct":22},"施工合同无效，已完工程质量不合格但修复后工程验收合格，发包人请求承包人承担修复费用",{"id":476,"libraryId":5,"type":15,"typeLabel":16,"stem":477,"options":478,"answer":24,"analysis":33},899005,"某进度款支付申请报告包含了下列内容：①累计已完成的合同价款；②累计已实际支付的合同价款；③本周期已完成的计日工价款；④本周期应扣回预付款。据此，发包人本周期应支付的合同价款是（ ）。",[479,481,483,485],{"key":20,"text":480,"correct":22},"①+②-③-④",{"key":24,"text":482,"correct":26},"①-②+③-④",{"key":28,"text":484,"correct":22},"②-①+③-④",{"key":31,"text":486,"correct":22},"①+②+③-④",{"id":488,"libraryId":5,"type":15,"typeLabel":16,"stem":489,"options":490,"answer":24,"analysis":33},899006,"在合同履行过程中由于违约解除合同的价款结算与支付说法正确的是（ ）。",[491,493,495,497],{"key":20,"text":492,"correct":22},"因承包人原因违约解除合同的，发包人也应按原支付周期支付已完成的合同价款",{"key":24,"text":494,"correct":26},"如果发包人应扣除的金额超过了应支付的金额，则承包人应在合同解除后的规定时间内将其差额退换给发包人",{"key":28,"text":496,"correct":22},"因发包人原因违约解除合同的，无须支付违约金",{"key":31,"text":498,"correct":22},"因发包人原因违约，费用由承包人提出，发包人核实后与承包人协商确定后的14天内向承包人签发支付证书",{"id":500,"libraryId":5,"type":15,"typeLabel":16,"stem":501,"options":502,"answer":31,"analysis":33},899007,"在进行竣工结算价款支付的过程中，以下做法错误的是（ ）。",[503,505,507,509],{"key":20,"text":504,"correct":22},"发包人应在收到承包人提交竣工结算款支付申请后规定时间内予以核实，向承包人签发竣工结算支付证书",{"key":24,"text":506,"correct":22},"发包人签发竣工结算支付证书后的规定时间内，按照竣工结算支付证书列明的金额向承包人支付结算款",{"key":28,"text":508,"correct":22},"发包人未按照规定的程序支付竣工结算款的，承包人可催告发包人支付，并有权获得延迟支付的利息",{"key":31,"text":510,"correct":26},"发包人逾期未支付竣工结算款时，除法律另有规定外，承包人可与发包人协商将该工程折价，也可直接向人民法院申请将该工程依法拍卖，发包人就该工程折价或拍卖的价款优先受偿",{"id":512,"libraryId":5,"type":15,"typeLabel":16,"stem":513,"options":514,"answer":31,"analysis":33},899008,"发包人应当开始支付不低于当年施工进度计划的安全文明施工费总额60％的期限是工程开工后的（ ）天内。",[515,516,517,519],{"key":20,"text":389,"correct":22},{"key":24,"text":391,"correct":22},{"key":28,"text":518,"correct":22},"21",{"key":31,"text":520,"correct":26},"28",{"id":522,"libraryId":5,"type":15,"typeLabel":16,"stem":523,"options":524,"answer":28,"analysis":33},899009,"在用起扣点计算法扣回预付款时，起扣点计算公式为T=P-（M\u002FN）则式中N是指（ ）。",[525,527,529,531],{"key":20,"text":526,"correct":22},"工程预付款总额",{"key":24,"text":528,"correct":22},"工程合同总额",{"key":28,"text":530,"correct":26},"主要材料及构件所占比重",{"key":31,"text":532,"correct":22},"累计完成工程金额",{"id":534,"libraryId":5,"type":15,"typeLabel":16,"stem":535,"options":536,"answer":20,"analysis":33},899010,"最终结清时，如果承包人被扣留的质量保证金不足以抵减发包人工程缺陷修复费用的，（ ）应承担不足部分的补偿责任。",[537,538,539,541],{"key":20,"text":256,"correct":26},{"key":24,"text":221,"correct":22},{"key":28,"text":540,"correct":22},"监理人",{"key":31,"text":542,"correct":22},"建设主管部门",{"id":544,"libraryId":5,"type":15,"typeLabel":16,"stem":545,"options":546,"answer":24,"analysis":33},899011,"最终结清是指合同约定的缺陷责任期终止后，承包人已按合同规定完成全部剩余工作且质量合格的，发包人与承包人结清全部剩余款项的活动，以下说法错误的是（ ）。",[547,549,551,553],{"key":20,"text":548,"correct":22},"缺陷责任期终止后，承包人已按合同规定完成全部剩余工作且质量合格的，发包人签发缺陷责任期终止证书",{"key":24,"text":550,"correct":26},"缺陷责任期终止后，承包人在合同内享有的索赔权利也自行终止",{"key":28,"text":552,"correct":22},"发包人收到承包人提交的最终结清申请单后的规定时间内予以核实，向承包人签发最终支付证书",{"key":31,"text":554,"correct":22},"发包人应在签发最终结清支付证书后的规定时间天内，按照最终结清支付证书列明的金额向承包人支付最终结清款",{"id":556,"libraryId":5,"type":15,"typeLabel":16,"stem":557,"options":558,"answer":24,"analysis":33},899012,"在施工合同履行期间，下列属于工程计量范围的是（ ）。",[559,561,563,565],{"key":20,"text":560,"correct":22},"工程变更修订的工程定额内容",{"key":24,"text":562,"correct":26},"合同文件中规定的各种费用支付项目",{"key":28,"text":564,"correct":22},"暂列金额中的计日工",{"key":31,"text":566,"correct":22},"擅自超出施工图纸施工的工程",{"id":568,"libraryId":5,"type":15,"typeLabel":16,"stem":569,"options":570,"answer":31,"analysis":33},899013,"在工程合同履行过程中出现施工合同无效导致价款纠纷的处理原则，以下说法正确的是（ ）。",[571,573,575,577],{"key":20,"text":572,"correct":22},"建设工程施工合同无效，则无论竣工验收是否合格，承包人请求支付工程价款的，均不予支持",{"key":24,"text":574,"correct":22},"建设工程施工合同无效，且建设工程经竣工验收不合格，修复后的建设工程经竣工验收合格，发包人承担修复费用",{"key":28,"text":576,"correct":22},"建设工程施工合同无效，且建设工程经竣工验收不合格，修复后的建设工程经竣工验收不合格，发包人应向承包人支付由此造成的损失费",{"key":31,"text":578,"correct":26},"没有资质的实际施工人借用有资质的建筑施工企业名义与他人签订建设工程施工合同的行为无效",{"id":580,"libraryId":5,"type":15,"typeLabel":16,"stem":581,"options":582,"answer":24,"analysis":33},899014,"某工程承包人向发包人递交了200万元的进度款支付申请。按照《建设工程工程量清单计价规范》GB50500-2013的规定，下列关于进度款支付的说法中，正确的是（ ）。",[583,585,587,589],{"key":20,"text":584,"correct":22},"向承包人支付不少于180万元的进度款",{"key":24,"text":586,"correct":26},"向承包人支付不少于120万元的进度款",{"key":28,"text":588,"correct":22},"向承包人支付不少于200万元的进度款",{"key":31,"text":590,"correct":22},"向承包人支付不少于100万元的进度款",{"id":592,"libraryId":5,"type":15,"typeLabel":16,"stem":593,"options":594,"answer":28,"analysis":33},899015,"下列文件和资料中，可作为建设工程工程量计量依据的是（ ）。",[595,597,599,601],{"key":20,"text":596,"correct":22},"造价管理机构发布的调价文件",{"key":24,"text":598,"correct":22},"造价管理机构发布的价格信息",{"key":28,"text":600,"correct":26},"质量合格证书",{"key":31,"text":602,"correct":22},"各种预付款支付凭证",{"id":604,"libraryId":5,"type":15,"typeLabel":16,"stem":605,"options":606,"answer":28,"analysis":33},899016,"下列建设工程施工合同无效情况下产生的价款纠纷，法院不予支持的是（ ）。",[607,609,611,613],{"key":20,"text":608,"correct":22},"工程竣工验收合格，承包人请求按合同支付工程价款",{"key":24,"text":610,"correct":22},"工程竣工验收不合格、但修复后合格，发包人要求承包人承担修复费用",{"key":28,"text":612,"correct":26},"工程竣工验收不合格、修复后仍不合格，承包人请求支付工程价款",{"key":31,"text":614,"correct":22},"承包人超越资质等级签订施工合同，但竣工前取得相应资质等级，请求按照有效合同处理",[616,619,622,625,628,631],{"id":15,"name":617,"category":7,"favorite":618},"领导干部任职前廉政法规知识测试题",92,{"id":620,"name":621,"category":7,"favorite":15},595,"建筑结构与设备",{"id":623,"name":624,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":626,"name":627,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":629,"name":630,"category":7,"favorite":8},534,"BIM工程师",{"id":632,"name":630,"category":7,"favorite":8},535]