[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900085":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900085,582,2,"多选题","（2020年真题）根据现行财务制度和企业会计准则，新增固定资产价值的内容包括（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","专有技术",false,{"key":16,"text":17,"correct":18},"B","建设单位管理费",true,{"key":20,"text":21,"correct":18},"C","土地征用费",{"key":23,"text":24,"correct":14},"D","银行存款",{"key":26,"text":27,"correct":18},"E","建筑工程设计费","BCE","P307-308 新增固定资产价值的内容包括:已投入生产或交付使用的建筑、安装工程造价;达到固定资产标准的设备、工器具的购置费用;增加固定资产价值的其他费用。其他费用包括建设单位管理费、土地征用费、地质勘察和建筑工程设计费、生产工艺流程系统设计费等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]