[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900084":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900084,582,2,"多选题","（2020年真题）根据现行《标准设计施工总承包招标文件》工程总承包项目合同中的暂列金额可用于支付签订合同时（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不可预见的变更设计费用",true,{"key":16,"text":17,"correct":14},"B","不可预见的变更施工费用",{"key":19,"text":20,"correct":21},"C","已知必然发生，但暂时无法确定价格的专业工程费用",false,{"key":23,"text":24,"correct":21},"D","已知必然发生，但暂时无法确定价格的工程设备购置费用",{"key":26,"text":27,"correct":14},"E","以计日工方式计价的工程变更费用","ABE","P274-280 暂列金额是指招标文件中给定的，用于在签订协议书时尚未确定或不可预见变更的设计、施工及其所需材料、工程设备、服务等的金额，包括以计日工方式支付的金额。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]