[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900078":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900078,582,2,"多选题","（2017年考题）根据建设工程工程量清单计价规范GB-50500-2013），关于工程竣工结算的计价原则，下列说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计日工按发包人实际签证确认的事项计算",true,{"key":16,"text":17,"correct":18},"B","总承包服务依据合同约定金额计算，不得调整",false,{"key":20,"text":21,"correct":14},"C","暂列金额应减去工程价款调整金额计算，余额归发包人",{"key":23,"text":24,"correct":14},"D","规费和税金应按国家或省级、行业建设主管部门的规定计算",{"key":26,"text":27,"correct":18},"E","总价措施项目应依据合同约定的项目和金额计算，不得调整","ACD","B选项：总承包服务费应依据合同约定金额计算，如发生调整的，以发承包双方确认调整的金额计算；E选项：措施项目中的总价项目应依据合同约定的项目和金额计算；如发生调整的，以发承包双方确认调整的金额计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]