[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900065":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900065,582,2,"多选题","（2017年考题）根据《建设工程工程量清单计价规范》（GB-50500-2013），关于计日工费的确认和支付，下列说法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人应按照确认的计日工现场签证报告核实该关项目的工程数量和单价",false,{"key":16,"text":17,"correct":18},"B","己标价工程量清单中有该类计日工单价的。按该单价计算",true,{"key":20,"text":21,"correct":14},"C","已标价工程量清单中没有该类计日工单价的，按承包人报价计算",{"key":23,"text":24,"correct":18},"D","计日工价款应列入同期进度款支付",{"key":26,"text":27,"correct":18},"E","发包人通知承包人以计日工方式实施的零星工作，承包人应予执行","BDE","A选项，单价按报价算；C选项，应由发承包双方按工程变更的有关规定商定。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]