[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900059":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900059,582,2,"多选题","（2020年真题）根据《建设工程施工合同（示范文本）》（GF-2017-0201），下列变化应纳入工程变更范围的有（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","改变墙体厚度",true,{"key":16,"text":17,"correct":18},"B","工程设备价格上涨",false,{"key":20,"text":21,"correct":18},"C","转由他人实施土石方工程",{"key":23,"text":24,"correct":14},"D","提高地基沉降控制标准",{"key":26,"text":27,"correct":14},"E","增加排水沟长度","ADE","P237-241 施工合同示范文本中工程变更范围：（1）增加或减少合同中任何工作，或追加额外的工作；（2）取消合同中任何工作，但转由他人实施的工作除外；（3）改变合同中任何工作的质量标准或其他特性；（4）改变工程的基线、标高、位置和尺寸；（5）改变工程的时间安排或实施顺序。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]