[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900055":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900055,582,2,"多选题","（2015年考题）在评标过程中，评标委员会可以要求投标人对投标文件有关文件作出必要澄清、说明和补充的情形包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投标文件未经单位负责人签字",false,{"key":16,"text":17,"correct":18},"B","对同类问题表述不一致",true,{"key":20,"text":21,"correct":18},"C","投标文件中有含义不明确的内容",{"key":23,"text":24,"correct":18},"D","有明显的计算错误",{"key":26,"text":27,"correct":14},"E","投标人主动提出的澄清说明","BCD","对投标文件的相关内容作出澄清、说明或补正，其目的是有利于评标委员会对投标文件的审查、评审和比较。澄清、说明或补正包括投标文件中含义不明确、对同类问题表述不一致或者有明显文字和计算错误的内容。但评标委员会不得向投标人提出带有暗示性或诱导性的问题，或向其明确投标文件中的遗漏和错误。同时，评标委员会不接受投标人主动提出的澄清、说明或补正。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]