[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900049":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900049,582,2,"多选题","（2017年考题）关于施工投标报价中下列说法中正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","投标人应逐项计算工程量，复核工程量清单",false,{"key":16,"text":17,"correct":14},"B","投标人应修改错误的工程量，并通知招标人",{"key":19,"text":20,"correct":21},"C","投标人可以不向招标人提出复核工程量中发现的遗漏",true,{"key":23,"text":24,"correct":21},"D","投标人可以通过复核防止由于订货超量带来的浪费",{"key":26,"text":27,"correct":21},"E","投标人应根据复核工程量的结果选择适用的施工设备","CDE","选项A，投标人应认真根据招标说明、图纸、地质资料等招标文件资料，计算主要清单工程量，复核工程量清单；选项B，复核工程量的目的不是修改工程量清单，即使有误，投标人也不能修改工程量清单中的工程量，因为修改了清单将导致在平表示认为投标文件未响应招标文件而被否决。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]