[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900047":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900047,582,2,"多选题","（2018年考题）关于工程施工项目最高投标限价编制的注意事项，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","未采用工程造价管理机关发布的工程造价信息时，应予以说明",true,{"key":16,"text":17,"correct":18},"B","施工机械设备的选型应本着经济实用、平均有效的原则确定",false,{"key":20,"text":21,"correct":18},"C","暂估价中的材料单价应通过市场调查确定",{"key":23,"text":24,"correct":14},"D","不可竞争措施项目费应按国家有关规定计算",{"key":26,"text":27,"correct":18},"E","竞争性措施项目费应依据经专家论证确认的施工组织设计或施工方案确定","AD","本题考查的是招标控制价的编制。选项B错误，施工机械设备的选型直接关系到综合单价水平，应根据工程项目特点和施工条件，本着经济实用、先进高效的原则确定。选项C错误，暂估价中的材料单价应按照工程造价管理机构发布的工程造价信息中的材料单价计算，工程造价信息未发布的材料单价，其单价参考市场价格估算。选项E错误，对于竞争性的措施费用的确定，招标人应首先编制常规的施工组织设计或施工方案，然后依据经专家论证确认后再进行合理确定措施项目与费用。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]