[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900041":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900041,582,2,"多选题","（2017年考题）采用全费用综合单价法编制施工图预算，下列说法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计算直接费后编制工料分析表",false,{"key":16,"text":17,"correct":18},"B","全费用综合单价中应包括规费和税金",true,{"key":20,"text":21,"correct":18},"C","综合计取的措施项目费以分部分项工程费和可计量的措施项目费之和为基数计算",{"key":23,"text":24,"correct":14},"D","编制综合单价分析表时，工料机消耗量与单价均应来自预算定额",{"key":26,"text":27,"correct":14},"E","分部分项工程量与措施项目费之和即为建筑安装工程施工图预算费用","BC","选项A，全费用综合单价法编制施工图预算的程序为：准备工作→计算分部分项工程量→套用综合单价→计算可计量措施项目费→计算综合计取的措施项目费→汇总造价。D选项，价格根据报告编制期的市场价格等因素确定；E选项，分部分项工程费与措施项目费之和即为建筑安装工程施工图预算费用。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]