[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900034":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900034,582,2,"多选题","（2018年考题）下列估算方法中，不适用于可行性研究阶段投资估算的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","生产能力指数",true,{"key":16,"text":17,"correct":14},"B","比例估算法",{"key":19,"text":20,"correct":14},"C","系数估算法",{"key":22,"text":23,"correct":24},"D","指标估算法",false,{"key":26,"text":27,"correct":14},"E","混合法","ABCE","本题考查的是静态投资部分的估算方法。在项目建议书阶段，投资估算的精度较低，可采取简单的匡算法，如生产能力指数法、系数估算法、比例估算法或混合法等，在条件允许时，也可采用指标估算法；在可行性研究阶段，投资估算精度要求髙，需采用相对详细的投资估算方法，即指标估算法。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]