[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900016":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900016,582,2,"多选题","（2017年考题）确定预算定额人工工日消耗量过程中，应计入其他用工的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","材料二次搬运用工",false,{"key":16,"text":17,"correct":18},"B","电焊点火用工",true,{"key":20,"text":21,"correct":14},"C","按劳动定额规定应增（减）计算的用工",{"key":23,"text":24,"correct":18},"D","临时水电线移动造成的停工",{"key":26,"text":27,"correct":14},"E","完成其一分项工程所需消耗的技术工种用工","BD","其他用工是辅助基本用工消耗的工日，包括超运距用工、辅助用工和人工幅度差用工。选项A，当实际工程现场运距超过预算定额取定运距时，可另行计算二次搬运费。C、E属于基本用工。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]