[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-900015":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},900015,582,2,"多选题","（2020年真题）关于人工定额消耗量的确定，下列算式正确的有（）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工序作业时间=基本工作时间×[1+辅助工作时间占比（%）]",false,{"key":16,"text":17,"correct":14},"B","工序作业时间=基本工作时间+辅助工作时间+不可避免中断时间",{"key":19,"text":20,"correct":21},"C","规范时间=准备与结束时间+不可避免中断时间+休息时间",true,{"key":23,"text":24,"correct":14},"D","定额时间=基本工作时间\u002F（1-辅助工作时间占比（%））",{"key":26,"text":27,"correct":21},"E","定额时间=（基本工作时间+辅助工作时间）\u002F（1-规范时间占比（%））","CE","P61-63",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]